File #: 22-0117    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 1/24/2022 In control: City Manager Procurement Awards
On agenda: 3/1/2022 Final action:
Title: Approve the award of Change Order #3 to Contract 19-112, Downtown Streetscape Phase II Design Engineering, to Civiltech Engineering for an amount not to exceed $8,850.15 and a total award of $229,086.57
Related files: 21-1332, 20-421, 19-532
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY MANAGER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Change Order #3 to Contract 19-112, Downtown Streetscape Phase II Design Engineering, to Civiltech Engineering for an amount not to exceed $8,850.15 and a total award of $229,086.57
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack

BACKGROUND:
In June 2019, the City Council approved an amendment to its Master Services Agreement with Civiltech Engineering to add Downtown Streetscape Phase II design engineering services in the amount of $128,831.35.

Civiltech was awarded the contract following issuance of RFP 19-112. This award produced the construction plan set for the 2020 Downtown Streetscape Improvement Project. Change order #1 in the amount of $9,968.64 was authorized on June 1, 2020 to support an additional round of reviews prior to final construction documents.

The construction documents were placed out for bid by the City with an initial construction start date of April 2020. However due to the COVID-19 pandemic, the construction contract was ultimately not awarded.

Through ongoing discussion with downtown stakeholders, the project was brought back to a vote before the Downtown Naperville Alliance (DNA) in October 2021. The direction received at that time was to modify the existing plans to include the north side of Jefferson Avenue between Main and Webster. Change Order #2 was approved by City Council on October 19, 2021 for $81,436.43 to retain Civiltech to make updates to the plan set and produce new construction documents with construction anticipated in spring 2022.

DISCUSSION:
Civiltech has prepared updated construction documents as outlined in previously approved Change Order #2. Those plans are currently advertised for bid. Construction is anticipated to begin March 1, 2022.

In preparation for the start of construction, City staff has been in coordination with the DNA to discuss project timeline, scope, impacts ...

Click here for full text