File #: 23-0149    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 2/3/2023 In control: City Council
On agenda: 3/7/2023 Final action: 3/7/2023
Title: Approve the award of Option Year Three to Contract 18-204, Large Diameter Water Meters, to Core & Main LP for an amount not to exceed $175,180.10 for a one-year term
Attachments: 1. WU019, 2. WU020
Related files: 21-1082, 21-1523, 18-790, 20-1160

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Option Year Three to Contract 18-204, Large Diameter Water Meters, to Core & Main LP for an amount not to exceed $175,180.10 for a one-year term

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In October 2018, the Council approved the award of Bid 18-204 to Core & Main LP for the purchase of large-diameter water meters, for a two-year term through December 31, 2020. The contract included three one-year options to extend and on November 4, 2020, and December 21, 2021 respectively, the Council approved the first and second option year renewals.

 

DISCUSSION:

Core & Main LP performed well during the first and second contract extensions. During that time, Water Utilities purchased 489 large water meters from this vendor. The meters range in size from 1.5 inches to six inches. All meters were delivered in a timely manner and with no issues. All new, large-diameter water meters will perform directly with the new AMI system.  Due to increase material and labor costs, Core & Main LP asked to extend the contract with a 3% increase in cost. The term of the third and final option year is January 1, 2023 through December 31, 2023 with no option year remaining.

 

FISCAL IMPACT:

CIP #: WU019 - Water Meter Additions & WU020 - Water Meter Replacements

 

Water meter additions and replacements are expensed to the infrastructure account listed below as part of the annual capital improvement program. A total of $1,350,000 is budgeted for new and replacement water meters in 2023. The requested award is within budget.

 

Account Number

Fund

Total Budget Amount

41252000-551502

Water Capital Fund

$39,813,900