File #: 22-0972    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 8/11/2022 In control: City Council
On agenda: 11/1/2022 Final action:
Title: Approve the award of Bid 22-223, Washington Street Sanitary Lateral Rehabilitation Project, to Performance Pipelining, Inc. for an amount not to exceed $273,130 for a six-month term
Attachments: 1. WW052
Related files: 20-175, 20-1045, 21-0968
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 22-223, Washington Street Sanitary Lateral Rehabilitation Project, to Performance Pipelining, Inc. for an amount not to exceed $273,130 for a six-month term
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In September 2022, Water Utilities issued Bid 22-223 for the rehabilitation of approximately 17 existing sanitary sewer service laterals by utilizing the installation of cured-in-place pipe (CIPP). The bid also includes the installation of approximately 11 Vac-A-Tee cleanouts and the installation of nine CIPP spot liners to cover abandoned laterals.

Lining service laterals have shown to be effective in reducing groundwater and rainfall-related infiltration and inflow into the sanitary sewer system. Excessive infiltration and inflow into the sanitary sewer system take up system conveyance capacity which may cause sanitary sewer overflows and sanitary sewer basement backups.

This work will be done prior to the Washington Streetscape project in 2023. Also, all work will be done during overnight hours so to minimize any traffic concerns. This work will not affect any winter operations.

DISCUSSION:

Advertisement Date:
09/23/2022
Notices Sent:
278
Opening Date:
10/12/2022
Planholders:
12


Proposals Received:|1010|
Bids were received from the following vendors:

Vendor Name
Proposed Cost
Engineer's Estimate
$269,910.00
Performance Pipelining Inc.
$273,130.00
Hoerr Construction
$317,165.00

* Resin and other material costs have increased during the bid process. The ongoing increase in material costs explains why the estimate is lower than the bid pricing.
.

The completion date of this project is April 30, 2023. The term of this contract is six months with no options to extend.

FISCAL IMPACT:
CIP #: WW052

Sanitary sewer and lateral lining services are expensed to the infrastructure account listed below a...