File #: 21-0852    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 6/22/2021 In control: City Manager Procurement Awards
On agenda: 8/1/2021 Final action:
Title: Approve the award of Change Order #2 to Contract 20-342, Police Department Exterior ADA Upgrades, to Lite Construction, Inc. for an amount not to exceed $1,444 and a total award of $240,844
Related files: 21-0146, 20-1111
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CHIEF PROCUREMENT OFFICER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Change Order #2 to Contract 20-342, Police Department Exterior ADA Upgrades, to Lite Construction, Inc. for an amount not to exceed $1,444 and a total award of $240,844
body

DEPARTMENT: Department of Public Works

SUBMITTED BY: Richard Dublinski, Director

BACKGROUND:
On October 6, 2020, the City Council awarded Contract 20-342, Police Department Exterior ADA Upgrades, to Lite Construction Inc. The award was to remove the existing 24-foot concrete walkway from the driveway circle to the entrance doors and replace it with a 12-foot walkway with snow melt tubing. The project also included the reconstruction of the ADA ramp between the driveway circle and walk as well as lighted bollards and vehicle barriers. Additional work included the removal of the existing sidewalk and brick pavers to be replaced with an 8-foot sidewalk at a corrected grade that meets ADA building code requirements.

The contract was awarded for $239,400 with a completion date of December 15, 2020. On February 20, 2021, change order #1 was approved to extend the project completion date 150 additional days.

DISCUSSION:
This change order is requested to pay for additional saw cutting performed by the contractor. When the original concrete sidewalk was removed it was discovered that the top of the building foundation was higher than expected resulting in the sidewalk only being 3" thick in this location. The new sidewalk depth of 5" and the insulation board and radiant heat that was to be installed was designed to be 9" of total depth so the top of the foundation was saw cut and concrete was removed to accomplish the design depth.

The amount of this change order exceeds the original contract amount by $1,444.00 and increases the original contract expiration date by 0 days.

I, Marc Noll, of DPW-PBO certify that this work is necessary for successful completion of this project. I further cer...