File #: 21-1207    Version: 1
Type: Resolution Status: Passed
File created: 9/13/2021 In control: City Council
On agenda: 11/16/2021 Final action: 11/16/2021
Title: Approve the award of Option Year Two to Contract 17-084, Riverwalk Consultant, to Engineering Resource Associates, Inc. for an amount not to exceed $362,500
Attachments: 1. Extension Letter - Naperville Riverwalk Consultant, 2. PA022, 3. PA034, 4. PA049, 5. PA051, 6. PA053
Related files: 17-306, 20-498, 20-1021, 21-0075, 21-0270, 23-0347, 23-1398
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Option Year Two to Contract 17-084, Riverwalk Consultant, to Engineering Resource Associates, Inc. for an amount not to exceed $362,500
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Naperville Riverwalk Commission ("Commission") engages an individual and/or professional firm capable of providing it with professional planning, architectural, engineering and construction management services.

The City Council awarded Contract 17-084 to Engineering Resource Associates, Inc. (ERA) on May 16, 2017 for a 43-month term from June 6, 2017 to December 31, 2020; with two, one-year options to extend. On October 20, 2020 the City Council awarded Option Year One for an amount not to exceed $167,500 for the purpose of providing ongoing engineering/design support to the Commission.

During the original term of the agreement, ERA provided assessment, analysis and prepared plans for the rehabilitation of the Moser Tower and Eagle Street walkway. ERA also assisted the Commission on the Riverwalk 2031 Master Plan. During the first one-year extension ERA continued support to the Commission along with resident engineering services for the construction work on the Moser Tower and Eagle Street walkway.

Based on the vendor's performance, the Transportation, Engineering, and Development (TED) Business Group recommends extending the contract for the second one-year option. ERA has agreed to maintain their rates and terms provided under the original contract.

DISCUSSION:
If outside funding becomes available, the Riverwalk Commission proposes to have design and permitting work performed on several projects during the second one-year option. In addition to supporting the Commission, ERA would also provide design services ranging from preliminary to final for the Eagle Street Gateway, the South Extension, the re-...

Click here for full text