File #: 20-1009    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 8/27/2020 In control: City Council
On agenda: 9/15/2020 Final action: 9/15/2020
Title: Approve the award of Change Order 1 to Contract 19-085, Improvements to City Wells 28 and 31, to Strand Associates for an amount not to exceed $59,761 and a total award of $143,382
Attachments: 1. WU029, 2. Signed approved CMO recommendation 19-085
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order 1 to Contract 19-085, Improvements to City Wells 28 and 31, to Strand Associates for an amount not to exceed $59,761 and a total award of $143,382
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Water Utilities owns and operates two deep wells, 28 and 31. The wells were drilled, and the original equipment was installed, in 1987 and 1989 respectively. Due to motor failure of Well 28, it is currently not in service. In 2016, Well 31 was reconditioned and equipped with a new 450 horsepower motor and bowl assembly. However, due to motor failure, Well 31 is also currently out of service.

In June 2019, Contract 19-085 was awarded to Strand Associates for the engineering design phase of improvements to Wells 28 and 31. The value of the original contract was $83,621. Design work on Well 31 was completed, and a construction contract was awarded, to AMS Mechanical Systems, Inc on July 21, 2020. A construction contract for Well 28 is recommended for award on September 15, 2020.

DISCUSSION:
During the design process, several tasks fell outside the consultant's approved scope of services as outlined in the contract.

These unanticipated tasks include:

1. Detailed analysis of potential to use sodium hypochlorite as a disinfectant. The analysis revealed cost and operational concerns; therefore, the facilities were designed to use chlorine gas as a disinfectant.
2. Additional work on the chlorine facilities at northwest water works, which is adjacent to Well 31.
3. Evaluation of VFDs and soft starters for the well motors.
4. Design of additional sanitary sewer at the Well 28 site.

For the items outlined above, staff recommends approval of Change Order 1 in an amount not to exceed $59,761 and a total award of $143,382.



FISCAL IMPACT:
CIP: WU029

Engineering design for the improvements to City wells is expensed ...

Click here for full text