File #: 18-261    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 3/23/2018 In control: City Council
On agenda: 5/15/2018 Final action:
Title: Approve the award of Bid 18-068, Transmission Tower Painting, to Morris Painting Inc. for an amount not to exceed $325,000, plus a 5% contingency
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 18-068, Transmission Tower Painting, to Morris Painting Inc. for an amount not to exceed $325,000, plus a 5% contingency
body

DEPARTMENT: Electric Utility

SUBMITTED BY: Mark Curran, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:Click here to enter text.
The Electric Utility has approximately 18.92 miles of overhead transmission lines consisting of 93 wood poles and 116 steel towers. Due to rust placement from long-term exposure to road salts, the steel towers require rust removal treatment and painting. This is both aesthetic and vital for tower reliability and strength.

In March 2018, the Electric Utility issued a bid for the surface preparation and painting of 42 138kV steel transmission towers located primarily along 75th Street from the Modaff Substation through the Meadows Substation to the ComEd metering point at Greene Road. No disruptions of service to the transmission line will be allowed during surface preparation and painting of towers and any adjacent conductors will be energized throughout the project. Nearly all transmission towers are over 100 ft. in height and will be painted from ground level to top. Therefore, it is vital that the contractor is experienced and qualified to work on structures of this magnitude and type.

DISCUSSION:

Advertisement Date:
03/07/2018
Notices Sent:
78
Opening Date:
03/23/2018
Planholders:
18


Bids Received:
2
The following bids were received:

Company Name
Bid Amount
BP & T Company
Non-Responsible
Morris Painting Inc.
$578,920

*The lowest bidder, BP & T Company was determined to be non-responsive because they could not demonstrate experience with 138kV tower painting or expertise to perform this work as solicited in the bid specifications. Morris Painting Inc., the lowest responsive and responsible bidder, is recommended for award.

The cost associated with the bid submitted by Morris Painting Inc. is over the amo...

Click here for full text