File #: 22-1065    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 8/31/2022 In control: City Manager Procurement Awards
On agenda: 9/1/2022 Final action:
Title: Approve the award of Change Order #6 to Contract 17-220, Washington Street Bridge Special Inspection Services, to Ciorba Group for an amount not to exceed $11,400 and a total award of $39,800.
Attachments: 1. 17-220 Change Order #6_Ciorba_2022_2023 Washington Street Inspections_20794.09_Ciorba Signed
Related files: 22-1593
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CHIEF PROCUREMENT OFFICER AUTHORITY PROCUREMENT AWARDS

 

ACTION REQUESTED:
title

Approve the award of Change Order #6 to Contract 17-220, Washington Street Bridge Special Inspection Services, to Ciorba Group for an amount not to exceed $11,400 and a total award of $39,800.

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William Novack, Director of TED / City Engineer

 

BACKGROUND:

The City Manager awarded Contract 17-220 to Ciorba Group to perform required monthly special feature inspections of the downtown Washington Street Bridge due to the current condition of the bridge. Ciorba has been performing the inspection every third inspection and City’s bridge program manager has been performing the other inspections.

 

DISCUSSION:

The City’s bridge program manager has recently relocated to another state, therefore can no longer perform the required monthly inspection. This change order is requested to add an additional six inspections to the contract so that Ciorba can perform the monthly inspections until April 2023, which is the date that the bridge is anticipated to be under construction.

 

FISCAL IMPACT:

CIP#: BR031

 

Washington Street Bridge Special Inspection Services are expensed to the Architect and Engineering Services account listed below.  A total of $360,000 has been budgeted for engineering for the Washington Street Bridge in 2022.  The requested change order is within the budgeted amount for this expense.

 

Account Number

Fund Description

Total Budget Amount

30282200-531309

Capital Projects Fund

$1,836,000