File #: 20-549    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 5/4/2020 In control: City Council
On agenda: 5/19/2020 Final action: 5/19/2020
Title: Approve the award of Procurement 20-205, South Central Interceptor Sewer Hardening and Protection - Phase III Construction Engineering Services, to Strand Associates for an amount not to exceed $207,500.
Attachments: 1. Prior Awards
Related files: 18-400
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Procurement 20-205, South Central Interceptor Sewer Hardening and Protection - Phase III Construction Engineering Services, to Strand Associates for an amount not to exceed $207,500.
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In 2016, the Water Utilities issued RFP 16-339 seeking the services of an engineering firm to perform preliminary engineering tasks and provide recommendations to harden, protect and preserve the long-term integrity of the south-central interceptor sewer located along the east bank of the West Branch of the DuPage River. As part of the RFP, the City included the option to use the services of the successful firm for future phases. Strand Associates (Strand) was awarded the contract for Phase I, which was completed in May 2017.

Due to the successful execution of Phase I outlined above, the City exercised its right to retain the services of Strand for Phase II of the project. Procurement 17-129 for Phase II Engineering Design was completed in February 2020.

DISCUSSION:
Strand performed well in Phase I and Phase II of the project. Staff recommends the City exercise its right to retain the services of Strand for Phase III of the project in order to maintain project continuity and efficiency. A significant component of this project is the DuPage County stormwater permit required because the contractor will be working adjacent to the DuPage River. Strand has unique knowledge regarding the permit that will be important if an issue arises during construction. Phase III of the south-central interceptor sewer project will consist of the following engineering services:

* Provide on-site construction inspection and oversight
* Review contractor shop drawings and submittals
* Attend monthly progress meetings
* Review change order requests and pay estimates
* Develop project record drawings
* Provide 2-...