File #: 23-1128    Version: 1
Type: Procurement Change Order Status: Passed
File created: 9/29/2023 In control: City Council
On agenda: 10/17/2023 Final action: 10/17/2023
Title: Approve the award of Change Order #1 to Option Year Three of Contract 18-258, Electric Utility Distribution, to Meade Inc. for an amount not to exceed $1,500,000 and a total award of $13,335,000
Related files: 18-1031, 20-1015, 21-1435, 23-1485
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #1 to Option Year Three of Contract 18-258, Electric Utility Distribution, to Meade Inc. for an amount not to exceed $1,500,000 and a total award of $13,335,000
body

DEPARTMENT: Electric Utility

SUBMITTED BY: Brian Groth, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Electric Utility (Utility) requires the services of an electrical contractor that can provide labor and equipment necessary for work that cannot be completed by the Utility due to time and staffing limitations. The assistance from Meade Inc., allows the Utility to meet customer and Capital Improvement Program (CIP) deadlines as well as respond to emergent work. To date Meade Inc. has completed work for the Utility, the Department of Public Works (DPW) and the Water Utility (WU). This collaborative approach has benefited all three departments by providing additional trained and qualified resources in a timely manner.

The City Council awarded Contract 18-258 to Meade Inc. on December 18, 2018, for a two-year term from January 1,2019 to December 31,2020 with three extensions. Option year one was approved on November 4,2020 and option years two and three were approved on December 07, 2021. The purpose of this contract is to offset and augment the services provided by the Utility.

DISCUSSION:
The Utility has two remaining Capital Improvement Projects (CIP) that must be completed by the end of this fiscal year. Work to be completed includes:
* Duct bank extension on Ogden Avenue from the IDOT storage yard to the Maserati dealership
* Edward Hospital Substation expansion project

The duct bank extension will allow the utility to underground 7,000 feet of overhead primary conductor in future years CIP projects. The Edward Hospital Substation expansion project is customer funded work which will improve reliability to the hospital and allow the Utility to store a spare power transformer, reducing outage time ...

Click here for full text