File #: 22-0805    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 6/29/2022 In control: City Manager Procurement Awards
On agenda: 8/1/2022 Final action:
Title: Approve the award of Change Order #6 to Contract 21-149, Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation, to StruxC-MC LLC, for an amount not to exceed $5,676.00 and a total award of $2,144,027.40
Attachments: 1. 21-149_MoserTower-CO06
Related files: 21-0402, 21-1373, 22-0687, 22-0689, 23-1225, 22-1066, 23-0084
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CHIEF PROCUREMENT OFFICER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Change Order #6 to Contract 21-149, Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation, to StruxC-MC LLC, for an amount not to exceed $5,676.00 and a total award of $2,144,027.40
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William Novack

BACKGROUND:
On June 1, 2021 the City Council awarded Contract 21-149, Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation, to StruxC-MC LLC. Work on Moser Tower include concrete repairs, addressing corroded steel surfaces, painting all the steel and replacing the staircase inside the tower. The Eagle Street walkway include removal and replacement of a failing deck beam and the associated railing work.

On November 16, 2021 the City Council approved Change Order #1 granting an additional 190 days to the contract due to delays encountered with coordinating relocation of the cell phone carrier transmitters on the tower.

On February 2, 2022 the Chief Procurement Officer approved Change Order #2 to add $2,470.00 of contingency for additional material.

On May 13, 2022 the City Manager approved Change Order #3 to add $13,530.40 of contingency to support changes to the pre-cast panels.

On June 8, 2022 the City Council approved Change Order #4 granting an additional 140 days to the contract due to supply chain delays with needed pre-cast materials.

On June 17, 2022 the City Manager approved Change Order #5 to add $30,199.00 of contingency to pay for scaffolding design and implementation in support the cell phone carrier relocations, and changes to light pole removals and modified pier foundation design.

The current construction end date for the project is September 30, 2022.

DISCUSSION:
This change order is requested to provide additional dollars to pay for additional concrete overlay on Entry Level 1 within the tower to provide pitch and transitions in two areas found to ha...