File #: 22-1066    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 8/31/2022 In control: City Manager Procurement Awards
On agenda: 10/1/2022 Final action:
Title: Approve the award of Change Order #7 to Contract 21-149, Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation, to StruxC-MC LLC, for an amount not to exceed $3,910.00 and a total award of $2,147,937.40
Attachments: 1. ProjPkg_21-149_MoserTower-CO07
Related files: 22-0805, 23-1225, 23-0084
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY MANAGER AUTHORITY PROCUREMENT AWARDS

 

ACTION REQUESTED:
title

Approve the award of Change Order #7 to Contract 21-149, Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation, to StruxC-MC LLC, for an amount not to exceed $3,910.00 and a total award of $2,147,937.40

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William Novack

 

BACKGROUND:

On June 1, 2021 the City Council awarded Contract 21-149, Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation, to StruxC-MC LLC. Work on Moser Tower include concrete repairs, addressing corroded steel surfaces, painting all the steel and replacing the staircase inside the tower. The Eagle Street walkway include removal and replacement of a failing deck beam and the associated railing work.

 

On November 16, 2021 the City Council approved Change Order #1 granting an additional 190 days to the contract due to delays encountered with coordinating relocation of the cell phone carrier transmitters on the tower.

 

On February 2, 2022 the Chief Procurement Officer approved Change Order #2 to add $2,470.00 of contingency for additional material.

 

On May 13, 2022 the City Manager approved Change Order #3 to add $13,530.40 of contingency to support changes to the pre-cast panels.

 

On June 8, 2022 the City Council approved Change Order #4 granting an additional 140 days to the contract due to supply chain delays with needed pre-cast materials.

 

On June 17, 2022 the City Manager approved Change Order #5 to add $30,199.00 of contingency to pay for scaffolding design and implementation in support the cell phone carrier relocations, and changes to light pole removals and modified pier foundation design.

 

On July 13, 2022 the Chief Procurement Officer approved Change Order #6 to add $5,676.00 of contingency to pay for additional concrete overlay and transition for two areas on Entry Level 1 within the tower.

 

The current construction end date for the project is September 30, 2022.

 

DISCUSSION:

This change order is requested to pay for a substitute material to be used for the concrete flooring finish. The original product specified was a one-step application but was found not to provide adequate working time in order to correctly apply over the large and complicated areas of this project. The new material is a two-step application which requires additional labor forces to return after initial application. This increase in labor was not originally accounted for in the bid price for this item of work.

 

The amount of this change order, inclusive of previously approved changes, exceeds the original contract amount by $55,785.40. No additional time request is made.

 

This contract was approved with contingency in the amount of 3% ($62,764.56) of the original contract value and 29 days. Staff requests the use of contingency funds for the change order. A summary of the award and contingency information is provided in the tables below.

 

Contingency

Authorized Contingency

Days

Dollars

Original Amount

29

$62,764.56

(-) Previously Authorized

330

$51,875.40

Subtotal

0

$10,889.16

(-) This Change

0

$3,910.00

Balance Left

0

$6,979.16

 

Contract Award

Original Contract Value

$2,092,152.00

Prior Cumulative Approved Change Orders

$51,875.40

Subtotal

$2,144,027.40

(+/-) This Change Order

$3,910.00

Total Contract Value

$2,147,937.40

 

 

FISCAL IMPACT:

CIP #: PA-048, PA-050

 

Moser Tower and Eagle Street Pedestrian Walkway Rehabilitation is expensed to the Building Improvements accounts listed below. No funds were budgeted for 2022 for this project as the original completion was scheduled for 2021. This change order of $3,910.00 will be accommodated from underspend in other TED capital projects, such as the MIP

 

Account Number

Fund Description

Total Budget Amount

30292300-551500

Bond Fund

$0

 

 

 

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.