22-1165
| 1 | 1. | Proclamation | Proclaim October 2022 as Disability Employment Awareness Month | | |
Action details
|
Video
|
22-1175
| 1 | 2. | Proclamation | Proclaim October 5, 2022 as Energy Efficiency Day in the City of Naperville | | |
Action details
|
Video
|
22-1180
| 1 | 1. | Minutes | Approve the regular City Council meeting minutes of September 20, 2022 | approved | Pass |
Action details
|
Not available
|
22-1186
| 1 | 2. | Meeting Schedule | Approve the City Council meeting schedule October, November and December 2022 | approved | Pass |
Action details
|
Not available
|
22-1185
| 1 | 3. | Appointment | Approve appointments to various Boards & Commissions | approved | Pass |
Action details
|
Not available
|
22-0980
| 1 | 4. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of Cooperative Procurement 22-256, SMARTnet Maintenance Renewal, to CDW-G for an amount not to exceed $230,777 and for a one-year term | approved | Pass |
Action details
|
Not available
|
22-0985
| 1 | 5. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of Bid 22-187, Aggregate Materials, to Green Dream International LLC for an amount not to exceed $413,634.90, and for a one-year term | approved | Pass |
Action details
|
Not available
|
22-1022
| 1 | 6. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of RFP 22-091, Emergency Notification Alert System Services, to Everbridge, Inc., for an amount not to exceed $214,744.33 and for a four-year term | approved | Pass |
Action details
|
Not available
|
22-1160
| 1 | 7. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of Cooperative Procurement 22-282 HPe Aruba 4001i Network Switches, to CDW Government for an amount not to exceed $259,807.60 | approved | Pass |
Action details
|
Not available
|
22-1146
| 1 | 8. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of Change Order #1 to Cooperative Procurement 22-061, Police Department Roof Restoration - Phase III and Final, to Weatherproofing Technologies Inc./Tremco for an additional 122 days | approved | Pass |
Action details
|
Not available
|
22-1158
| 1 | 9. | Change Order & Work Order | Approve the award of Change Order #1 to RFQ Work Order 17-122-TED-2201, Phase III Downtown Streetscape Improvements, to Civiltech Engineering Inc. for an amount not to exceed $98,337.00 and a total award of $493,431 | approved | Pass |
Action details
|
Not available
|
22-1154
| 1 | 10. | Change Order & Work Order | Approve the award of Change Order #4 to Contract 22-035, 2022 Downtown Streetscape Construction, to RW Dunteman Co. for an amount not to exceed $44,423.98 and a total award of $4,933,925.92 and for an additional 46 days | approved | Pass |
Action details
|
Not available
|
22-1064
| 1 | 11. | Extension of Agreement | Approve the award of Option Year Three of Contract 20-001, Pipefitting, Plumbing and Mechanical Services, to Dahme Mechanical Industries, Inc. for the amount to not exceed $210,560 | approved | Pass |
Action details
|
Not available
|
22-1156
| 1 | 12. | Change Order & Work Order | Approve the award of Change Order #1 to Option Year Two of Contract 18-022, Motor Fuel Tank Wagon, to Heritage FS, Inc., for an amount not to exceed $70,000 and a total award of $235,000 | approved | Pass |
Action details
|
Not available
|
22-1136
| 1 | 13. | Change Order & Work Order | Approve the award of Change Order #1 to Option Year Three of Contract 18-025, Motor Fuel, to Luke Oil for an amount not to exceed $270,000 and a total award of $1,270,000 | approved | Pass |
Action details
|
Not available
|
22-1145
| 1 | 14. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of Change Order #1 to Bid 21-245, Central Parking Facility - LED Lighting Retrofit, to Rag’s Electric Inc. for an additional 273 days | approved | Pass |
Action details
|
Not available
|
22-1181
| 1 | 15. | Change Order & Work Order | Approve the award of Change Order #1 to Bid 22-036, Landscape Restoration Services, to Semper Fi Landscaping Inc. and Local Lawn Care and Landscaping for an amount not to exceed $165,000 and a total award of $490,000 | approved | Pass |
Action details
|
Not available
|
22-1182
| 2 | 16. | Public Improvements | Accept the public underground improvements for Heritage Place Phase I and IA and authorize the City Clerk to reduce the corresponding public improvement surety | approved | Pass |
Action details
|
Not available
|
22-1163
| 1 | 17. | Resolution | Adopt the resolution approving the Intergovernmental Agreement between the County of DuPage and the City of Naperville for Improvement of CH23/Naperville Road from Naperville-Wheaton Road/Ridgeland Avenue to Diehl Road, Section No. 16-00195-06-CH | adopted | Pass |
Action details
|
Not available
|
22-1184
| 1 | 18. | Resolution | Adopt the resolution approving the Intergovernmental Agreement between Will County and the City of Naperville for placement of license plate recognition cameras located on Will County rights-of-way | adopted | Pass |
Action details
|
Not available
|
22-1177
| 1 | 1. | Public Hearing | Conduct the public hearing and direct staff to prepare ordinances approving the Heinen Business District Plan and setting an associated Business District tax of one-half of one percent | closed | Pass |
Action details
|
Video
|
22-0988C
| 1 | 1. | Ordinance | Option A: Concur with the Planning and Zoning Commission and the petitioner and pass the ordinance approving a variance to Section 6-6A-7 for the property located at 620 N Sleight Street - PZC 22-1-068; or Option B: Concur with staff and deny the variance - PZC 22-1-068 | passed | Pass |
Action details
|
Video
|
22-1162
| 1 | 1. | BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR | Approve the award of RFQ 22-255, Polyethylene/PVC Conduit Qualifications, to Power Line Supply, Universal Utility Supply, and Wesco Distribution as approved vendors for future projects, for an amount not to exceed $1,387,000 and for a one-year term | approved | Pass |
Action details
|
Video
|
22-0258
| 1 | 1. | Report | Provide direction regarding construction and location of noise walls for the 248th Avenue improvement project | directed staff | |
Action details
|
Video
|
22-0258
| 1 | | Report | Provide direction regarding construction and location of noise walls for the 248th Avenue improvement project | directed staff | Fail |
Action details
|
Video
|
22-0258
| 1 | | Report | Provide direction regarding construction and location of noise walls for the 248th Avenue improvement project | directed staff | Pass |
Action details
|
Video
|
22-0505D
| 1 | 2. | Report | Consider the three options regarding the Affordable Housing Incentive Program and direct staff accordingly - PZC 22-1-017 | tabled | Pass |
Action details
|
Video
|
22-1179
| 1 | 3. | Report | Receive the City of Naperville Bridge to 2023 Priorities Plan fall 2022 status update | | |
Action details
|
Video
|