22-1471
| 1 | 1. | Presentation | Presentation of Fire Chief’s Awards | | |
Action details
|
Video
|
22-1428
| 1 | 1. | Minutes | Approve the regular City Council meeting minutes of November 15, 2022 | approved | Pass |
Action details
|
Not available
|
22-1474
| 1 | 2. | Meeting Schedule | Approve the City Council meeting schedule for December 2022 through February 2023 | approved | Pass |
Action details
|
Not available
|
22-1251
| 1 | 3. | Procurement Award | Approve the award of Cooperative Procurement 22-335, High Cube Camera Van Replacement (Unit 780), to Elxsi (dba CUES) for an amount not to exceed $599,408 | approved | Pass |
Action details
|
Not available
|
22-1295
| 1 | 4. | Procurement Award | Approve the award of Sole Source Procurement 22-329, Naper Boulevard Stormwater Lift Station Upgrade of Vaughan Model S8N-151 Submersible Chopper Pump, to Gasvoda & Associates, Inc., for an amount not to exceed $249,989.00 | approved | Pass |
Action details
|
Not available
|
22-1345
| 1 | 5. | Procurement Award | Approve the award of Option Year One to Bid 21-394, Electrician Services, to Volt Electric Inc. for an amount not to exceed $226,917 | approved | Pass |
Action details
|
Not available
|
22-1421
| 1 | 6. | Procurement Award | Approve the award of Option Year One to Contract 21-382, Parkway Tree Trimming Services, to Steve Piper and Sons Inc. for an amount not to exceed $52,500 and for a one-year term | approved | Pass |
Action details
|
Not available
|
22-1392
| 1 | 7. | Procurement Award | Approve the award of Option Year Three to Contract 18-027, Architectural and Engineering Services, to Kluber Architects and Engineers and Legat Architects, Inc. for an amount not to exceed $125,000 | approved | Pass |
Action details
|
Not available
|
22-1429
| 1 | 8. | Procurement Award | Approve the award of Bid 22-200, Emergency Medical Services (EMS) Supplies, to Medline Industries Holding, L.P., for an amount not to exceed $122,156.22 and for a one-year term | approved | Pass |
Action details
|
Not available
|
22-1397
| 1 | 9. | Procurement Award | Approve the award of RFP 22-274, Riverwalk Design Consultant, to Engineering Resource Associates, Inc. for an amount not to exceed $912,500 and for a three-year term | approved | Pass |
Action details
|
Not available
|
22-1407
| 1 | 10. | Procurement Award | Approve the award of RFP 22-278, Springbrook Water Reclamation Center South Plant RAS Grit Improvements project, to Donohue & Associates, Inc. for an amount not to exceed $853,000, plus a 3% contingency | approved | Pass |
Action details
|
Not available
|
22-1415
| 1 | 11. | Procurement Award | Approve the award of Bid 22-310, Grand Pavilion and Covered Bridge Roof Replacements, to Filotto Roofing, for an amount not to exceed $133,500.00 plus a five percent contingency | approved | Pass |
Action details
|
Not available
|
22-1419
| 1 | 12. | Procurement Award | Approve the award of Change Order #1 to Contract 22-280, Trip Hazard Removal Program, to ASTI Sawing Inc. for an amount not to exceed $112,904.82 and a total award of $179,276.22 and for an additional 162 days | approved | Pass |
Action details
|
Not available
|
22-1445
| 1 | 13. | Procurement Award | Approve the award of Cooperative Procurement 22-351, Compact Wheel Loader Replacement (Unit 898), to Alta Equipment Company for an amount not to exceed $103,339 | approved | Pass |
Action details
|
Not available
|
22-1380
| 1 | 14. | Procurement Change Order | Approve the award of Change Order #1 to Option Year Four of Contract 17-182, Security Camera Installation, to Pace Systems for an amount not to exceed $250,000 and a total award of $600,000 and an additional two years | approved | Pass |
Action details
|
Not available
|
22-1393
| 1 | 15. | Procurement Change Order | Approve the award of Change Order #1 to Contract 22-020, Summerfield Lift Station Rehabilitation, to Marc Kresmery Construction, LLC. for an additional 167 days | approved | Pass |
Action details
|
Not available
|
22-1396
| 1 | 16. | Procurement Change Order | Approve the award of Change Order #1 to Contract 22-030, Northeast Waterworks Phase 1 Improvements, to Dahme Mechanical Industries, Inc. for an additional 288 days | approved | Pass |
Action details
|
Not available
|
22-1399
| 1 | 17. | Procurement Change Order | Approve the award of Change Order #4 to Contract 19-214, Water Advanced Metering Infrastructure (AMI) Project, to Core & Main LP for an additional 365 days (Item 1 of 2) | approved | Pass |
Action details
|
Not available
|
22-1402
| 1 | 18. | Procurement Change Order | Approve the award of Change Order #3 to Contract 20-322, Water Utilities Meter Data Management Software and Support (AMI Project), to Harris Computer Systems for an additional 365 days (Item 2 of 2) | approved | Pass |
Action details
|
Not available
|
22-1403
| 1 | 19. | Procurement Change Order | Approve the award of Change Order #2 to Contract 21-223, Springbrook Water Reclamation Center Influent Flow Meter Replacement, to Dahme Mechanical Industries, Inc. for an additional 181 days | approved | Pass |
Action details
|
Not available
|
22-1408
| 1 | 20. | Procurement Change Order | Approve the award of Change Order #2 to Contract 20-052, Springbrook Water Reclamation Center Facilities Plan Phase II, to Donohue and Associates for an amount not to exceed $210,000 and a total award of $965,630 | approved | Pass |
Action details
|
Not available
|
22-1416
| 1 | 21. | Procurement Change Order | Approve the award of Change Order #1 to Option Year Three of Contract 19-074, Commercial Garage Door, Man Door and Security Gate Services, to Allied for an amount not to exceed $46,000 and a total award of $131,721 | approved | Pass |
Action details
|
Not available
|
22-1418
| 1 | 22. | Procurement Change Order | Approve the award of Change Order #1 to Option Year Three of Contract 18-012, IDenticard Building Access Control, to Pace Systems for an amount not to exceed $92,340 and a total award of $136,840 and an additional two years | approved | Pass |
Action details
|
Not available
|
22-1460
| 1 | 23. | Procurement Change Order | Approve the award of Change Order #1 to Contract 21-189, Unit 259 (Tandem Axle Dump Truck) Equipment Replacement, to JX Peterbilt for an amount not to exceed $15,333.73 and a total award of $245,298.21 | approved | Pass |
Action details
|
Not available
|
22-1484
| 1 | 24. | Report | Approve the recommended adjustment to non-union employee pay ranges | approved | Pass |
Action details
|
Not available
|
22-1455
| 1 | 25. | Ordinance | Waive the first reading and pass the ordinance amending Section 11-4 of the Naperville Municipal Code repealing bicycle registration and license requirements (requires 6 positive votes) | passed | Pass |
Action details
|
Not available
|
22-1280B
| 1 | 26. | Ordinance | Pass the ordinance approving a major change to the Bradford Commons PUD to grant a deviation to the off-street parking requirements, final PUD plat, controlling elevations, and controlling landscape plan for 2703 Beebe Drive (Wu’s House) - PZC 22-1-073 | passed | Pass |
Action details
|
Not available
|
22-1404B
| 1 | 27. | Ordinance | Pass the ordinance approving a conditional use in the B3 District for an automobile service station located at 1304 Plainfield/Naperville Road (Casey’s) - PZC 22-1-051 | passed | Pass |
Action details
|
Not available
|
22-1467
| 1 | 28. | Ordinance | Conduct the first reading of the ordinance approving a policy for interconnection and fair crediting of customer renewable self-generation and storage facilities and amending Sections 6-15 and 8-1 of the Naperville Municipal Code | passed | Pass |
Action details
|
Not available
|
22-0505E
| 1 | 29. | Report | Continue discussion of the Affordable Housing Incentive Program to the January 17, 2023 City Council meeting - PZC 22-1-017 | approved | Pass |
Action details
|
Not available
|
22-1446
| 1 | 1. | Public Hearing | Conduct the public hearing for the 2023 Annual Budget (Item 1 of 2) | closed | Pass |
Action details
|
Video
|
22-1447
| 1 | 2. | Ordinance | Pass the ordinance adopting the 2023 Annual Budget in the amount of $603,462,981 (Item 2 of 2) | passed | Pass |
Action details
|
Video
|
22-1431
| 1 | 3. | Public Hearing | Receive the staff report and conduct the public hearing for property located at the northeast corner of Nannyberry Street and 103rd Street (Ashwood Heights Unit 2) - PZC 22-1-002 (Item 1 of 3) | received | Pass |
Action details
|
Video
|
22-1432
| 1 | 4. | Ordinance | Pass the ordinance authorizing the execution of an amendment to the Ashwood Park (A/K/A 248th Assemblage Center) Annexation Agreement for the Ashwood Heights Unit 2 Subdivision - PZC 22-1-002 (requires six positive votes) (Item 2 of 3) | passed | Pass |
Action details
|
Video
|
22-1433
| 1 | 5. | Ordinance | Pass the ordinance approving the preliminary/final plat of subdivision for property located at the northeast corner of Nannyberry Street and 103rd Street (Ashwood Heights Unit 2) - PZC 22-1-002 (Item 3 of 3) | passed | Pass |
Action details
|
Video
|
22-1463
| 1 | 6. | Public Hearing | Conduct the public hearing for the stormwater variance request for the North Aurora Road Underpass project at the Canadian National Railway (Item 1 of 2) | closed | Pass |
Action details
|
Video
|
22-1464
| 1 | 7. | Ordinance | Pass the ordinance approving a stormwater variance to Section 15-72 D.3 of the DuPage Countywide Stormwater and Floodplain ordinance for the North Aurora Road underpass project at the Canadian National Railway (Item 2 of 2) | passed | Pass |
Action details
|
Video
|
22-1424
| 1 | 1. | Report | Receive the report and concur with staff recommendations for Washington Street Streetscape Option 3 and Main Street Streetscape Option B | received | Pass |
Action details
|
Video
|
22-1472
| 1 | 2. | Report | Receive the report and concur with PUAB recommendation to fund the 2023 Renewable Energy Program at the 2022 revenue level and dedicate any underspend to installing solar projects on City of Naperville facilities | | |
Action details
|
Video
|