File #: 22-1558    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 12/12/2022 In control: City Council
On agenda: 1/17/2023 Final action:
Title: Approve the award of Change Order #2 to Option Year 1 of Contract 19-273, Traffic Signal and Street Light Maintenance, to Meade, Inc. for an amount not to exceed $32,303.23 and a total award of $905,617.74
Related files: 23-0607
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #2 to Option Year 1 of Contract 19-273, Traffic Signal and Street Light Maintenance, to Meade, Inc. for an amount not to exceed $32,303.23 and a total award of $905,617.74
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
This contract is for a traffic signal and street light maintenance services at signalized intersections.

On October 1, 2019, the City Council awarded Contract 19-273 to Meade Inc. for a two-year term from December 1, 2019 to November 31, 2021 with one, two-year option to extend. On October 19, 2021, the City Council awarded the two-year option.

A portion of the contract is dedicated to scheduled or emergency replacement of failed equipment or third-party damage primarily resulting from vehicle crashes. While the contract is sufficient to cover several instances involving minor emergency work, additional funds are needed to reimburse the contractor for major repairs or when the number of repairs exceeds expectations. The contract provided $78,000 for knockdown repairs during its entire two-year extension period, and repairs this year are in excess of $170,000.

On September 6, 2022, the City Council awarded Change Order #1 to add $96,487.97 to the contract. This change order covered three major repairs from vehicle crashes that damaged traffic signal equipment.

DISCUSSION:
This Change Order is requested to add funds to the maintenance contract to cover repair costs associated with the following three crashes involving traffic signal damage. Per the contract, these repairs are billed on a "time and materials" basis.

* On November 18, 2022, a crash occurred at Washington Street and Naper Boulevard that damaged the traffic signal cabinet, and the repairs cost $19,865.16.

* On November 25, 2022, a crash occurred at Aurora Avenue and West Street that knocked do...