File #: 21-1164    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 9/2/2021 In control: City Manager Procurement Awards
On agenda: 1/1/2022 Final action:
Title: Approve the award of Change Order #3 to Contract 21-001, 2021 Street Resurfacing Program - MFT, to K-Five Construction Corporation to reduce the contract amount by $319,609.02 for a total amount not to exceed $3,429,905.08
Attachments: 1. 21-001-CO_2, 2. 2021 Final_Balancing_Change_Order Justification
Related files: 21-0973, 21-0306
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY MANAGER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Change Order #3 to Contract 21-001, 2021 Street Resurfacing Program - MFT, to K-Five Construction Corporation to reduce the contract amount by $319,609.02 for a total amount not to exceed $3,429,905.08
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack

BACKGROUND:
The City Council awarded Contract 21-001 to K-Five Construction Corporation on April 20, 2021, with a completion date of July 16, 2021. The purpose of this contract is to resurface various City streets as part of the annual street maintenance program.

The Chief Procurement Officer awarded Change Order #1 for an amount of $10,000 on July 9, 2021. Change Order #2 was approved by the Chief Procurement Officer on July 26, 2021 to extend the contract for an additional 7 days.

DISCUSSION:
This contractor has completed all the work required within the contract. This is a final balancing change order which includes changes in previously approved authorizations. It compares the original awarded quantities and costs with the as-built quantities as measured in the field and accounts for all changes in quantity and cost for each pay item and the overall contract value. The total net amount of all change orders including this final balancing change order decreases the original amount by $319,609.02 and by 0 days. A detailed explanation of the justification for each pay item is attached.

Contract Award
Original Contract Value
$3,739,514.10
Prior Cumulative Approved Change Orders
$10,000.00
Subtotal
$3,749,514.10
(+/-) This Change Order
($319,609.02)
Total Contract Value
$3,429,905.08

Contingency
Authorized Contingency
Days
Dollars
Original Amount

$186,975.71
(-) Previously Authorized

$10,000.00
Subtotal

$176,975.71
(-) This Change

$0
Balance Left

$176,975.71



FISCAL IMPACT:
CIP #:MP009

The change order reduces the contract amount by $319,609.02 for a total amount not to e...

Click here for full text