File #: 20-1506    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 12/10/2020 In control: City Manager Procurement Awards
On agenda: 1/1/2021 Final action:
Title: Approve the award of Change Order #2 to Contract 20-004, 2020 Street Resurfacing Program - MFT, to R.W. Dunteman to reduce the contract award amount by $531,149.52, 9.89% and a total amount not to exceed $4,916,750.48 and by 0 days
Related files: 20-735, 20-399, 21-0205
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY MANAGER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Change Order #2 to Contract 20-004, 2020 Street Resurfacing Program - MFT, to R.W. Dunteman to reduce the contract award amount by $531,149.52, 9.89% and a total amount not to exceed $4,916,750.48 and by 0 days
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BACKGROUND:
The City Council awarded Contract 20-004 to R.W. Dunteman on April 21, 2020 with a completion date of August 14, 2020. The purpose of this contract is to resurface various city streets as part of the annual street maintenance program.

Change order #1 was previously approved, increasing the contract amount by $78,900.

DISCUSSION:
This change order is requested in order to balance certain pay items. Upon receipt of information for Item #4, a final balancing change order for the project will be submitted.

There are a couple reasons for the reduction. One is we eliminated the resurfacing of the four streets/blocks around Little Friend's property due to pending development and potential work within the roadway. Second is we eliminated the resurfacing of Jefferson Avenue from Court Place to Washington to accommodate restaurants' outdoor dining on the street. Another reason is we changed the resurfacing cross section of some streets by switching from poly binder to surface course due to street's condition, as well as surface course's unit price is more than 10% less than poly binder.

The amount of this change order decreases the contract amount by $531,149.52 and there is no change to the original contract expiration date.

I, Yifang Lu, of TED certify that this work is necessary for successful completion of this work/project/contract. I further certify that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed, or the change is germane to the original contract as signed, o...

Click here for full text