File #: 22-0901    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 8/1/2022 In control: City Council
On agenda: 9/6/2022 Final action: 9/6/2022
Title: Approve the award of Bid 22-224, 2022 New Sidewalk Program, to Triggi Construction, Inc, for an amount not to exceed $304,684.26, plus a 5% contingency
Attachments: 1. MP009, 2. CS006
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 22-224, 2022 New Sidewalk Program, to Triggi Construction, Inc, for an amount not to exceed $304,684.26, plus a 5% contingency
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The purpose of the Comprehensive Sidewalk Plan is to improve walkability throughout the City.

In 2019, the selection process for the New Sidewalk Program was revised to better prioritize the remaining sidewalk gaps in the City. As a result, a two-year program was created and approved by both the Transportation Advisory Board (TAB) and the City Council. The first year of the program was constructed in 2021 and this award is for the second year of the program.

In July 2022, the Transportation, Engineering and Development (TED) Business Group issued Bid 22-224, 2022 New Sidewalk Program. This bid included a base bid and three alternatives in an effort to optimize the size of the program under the current market conditions. The base bid consisted of the remaining sidewalk gaps approved in 2019 and a retaining wall required near one contingency location to accommodate sidewalk modifications. Each alternative bid cumulatively adds one contingency location. The gap locations are listed below.

Base Bid:
* Aurora Avenue, south side between IL Rt 59 and Westridge Court
* Porter Avenue, north side between Julian St and White Oak Dr
* Sleight Street, west side between Hillside Rd and Prairie Ave
* Wellner Rd, east side between Loomis St and Sleight St
* Webster St, northwest corner with 11th St; retaining wall for sidewalk modifications

Alternative 1: adds Benton Avenue, north side between Fremont St and West St
Alternative 2: adds Webster Street, east side between 10th Ave and 11th Ave
Alternative 3: adds Cottage Street, south side between Fremont St and West St

DISCUSSION:

Advertisement Date:
07/18/22
Notices Sent:
...

Click here for full text