File #: 22-0823    Version: 1
Type: Change Order & Work Order Status: Passed
File created: 7/5/2022 In control: City Council
On agenda: 7/19/2022 Final action: 7/19/2022
Title: Approve the award of Change Order #1 to Contract 20-052, Springbrook Water Reclamation Center Facilities Plan Phase II, to Donohue and Associates for an amount not to exceed $73,910 and a total award of $755,630
Attachments: 1. WW044
Related files: 21-0090, 20-685, 23-1388, 22-1408
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #1 to Contract 20-052, Springbrook Water Reclamation Center Facilities Plan Phase II, to Donohue and Associates for an amount not to exceed $73,910 and a total award of $755,630
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
On June 16, 2020, the City Council awarded Contract 20-052 to Donohue and Associates, Inc. for an amount not to exceed $255,950 to complete an existing facility asset evaluation, conduct a disinfection alternatives analysis and develop a Facilities Plan for the Springbrook Water Reclamation Center (SWRC). The original contract award allowed the option to use the vendor's services for future phases, including engineering design of disinfection improvements identified during the disinfection alternatives analysis.

On May 18, 2021, the City Council awarded Contract 20-052, Springbrook Water Reclamation Center Facilities Plan Phase II, to Donohue and Associates, Inc. for an amount not to exceed $681,720. This work included the following engineering services:

1. Pre-selection of equipment;
2. Preliminary engineering;
3. Final engineering, preparation of final plans and specifications;
4. IEPA and City-required permitting;
5. Construction services including shop drawing review, responding to RFI's, field visits and preparation of record drawings.

The engineering design phase of the project is substantially complete, with the construction phase services remaining in the contract.

DISCUSSION:
During the completion of these engineering services, it was determined by the City that certain additional services were beneficial to the quality of the project, schedule of delivery and overall cost to the City due to unexpected project needs and the evolving market conditions brought on by the economic recovery related to the COVID-19 pandemic. These services included wetland delineation and co...

Click here for full text