File #: 21-0391    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 3/12/2021 In control: City Council
On agenda: 4/7/2021 Final action:
Title: Approve the award of Bid 21-004, 2021 Patching Program, to J.A. Johnson Paving Company for an amount not to exceed $434,150, plus a 5% contingency
Attachments: 1. CIP PAGE
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 21-004, 2021 Patching Program, to J.A. Johnson Paving Company for an amount not to exceed $434,150, plus a 5% contingency
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Transportation, Engineering and Development (TED) Business Group issued Bid 21-004 seeking contractors to perform annual street patching throughout the City. The project involves replacing isolated sections of deteriorated pavement with hot-mix asphalt to varying depths, depending upon severity. The strategy is used on streets in relatively good condition but exhibiting isolated defects. Additionally, this project will install permanent patches to take care of potholes that developed over the winter months. This maintenance program prolongs the life of streets, ultimately saving money.

DISCUSSION:

Advertisement Date:
02/22/21
Notices Sent:
109
Opening Date:
03/12/21
Planholders:
8


Proposals Received:
5

Bids were received from the following vendors:

Vendor Name
Proposed Cost
Engineer's Estimate
$507,350
J.A. Johnson Paving Company
$434,150
Geneva Construction
$574,265
Chicagoland Paving Contractors, Inc.
$750,000
Brothers Asphalt Paving, Inc.
$816,314.82
Schroeder Asphalt Services, Inc.
$916,375

The engineers estimate is based on the contract unit prices from the 2019 and 2020 patching programs, adjusted 5% to account for inflation. The low bid is within 14.4% of the engineer's estimate and significantly less than the other bids received. The low bidder has performed the Patching Program in past years without issues.

The completion date of this project is October 1, 2021.


FISCAL IMPACT:
CIP #: MP009 - Street Maintenance Improvement Program (MIP)

The 2021 Patching Program is expensed to the Infrastructure account listed below. The Patching program is a part of the overall MIP, for which $12,000,00...