File #: 21-0068    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 1/8/2021 In control: City Council
On agenda: 3/2/2021 Final action: 3/2/2021
Title: Approve the award of Bid 21-088, Central Parking Facility Maintenance Improvements, to J. Gill and Company, for an amount not to exceed $1,009,526.13, plus a 3% contingency
Related files: 19-530, 20-308, 20-1494, 21-1019

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 21-088, Central Parking Facility Maintenance Improvements, to J. Gill and Company, for an amount not to exceed $1,009,526.13, plus a 3% contingency

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Richard Dublinski, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Central Parking Facility, Van Buren, and Water Street parking decks were built in 1987, 2000, and 2015 respectively. An assessment completed in 2017 revealed that these decks require repair, renovations, and on-going maintenance. The Central Parking Facility, the oldest of the City’s parking structures, is an approximately 151,000 square foot, three-level precast double tee structure. The 2017 assessment identified this structure as having the highest repair and maintenance priority due to age-related deterioration and corrosion.

 

In 2019, staff retained the services of Walker Consultants to assist with evaluating, prioritizing, programming, engineering, and managing parking facility projects starting with the Central Parking Facility. The findings listed in Walker Consultants’ pre-engineering evaluation are consistent with those highlighted in the initial assessment. 

 

In February 2021, DPW issued Bid 21-088, Central Parking Facility Maintenance Improvements, to contract with a company to perform a complete rehabilitation of the top and middle levels of the Central Parking Facility. The work in the base bid includes repairs to tee flanges, tee stems, beams, columns and walls.  Additional work includes the replacement of floor sealants, expansion joints, and floor drains.  Two alternate options were included as part of the bid for the application of a traffic coating on the top level and for painting the ceiling, beams, walls and columns on all levels.

 

DISCUSSION:

 

Advertisement Date:

02/02/21

Notices Sent:

141

 

02/17/21

Planholders:

29

 

 

Proposals Received:

07

 

 

 

 

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Total Cost

J. Gill & Company

$979,526.13

JLJ Contracting

$1,252,935

National Restoration Systems, Inc.

$1,494,545

Bulley & Andrews Concrete Restoration

$1,812,287

Cruz Brothers Construction Company

$1,823,682

Allied Waterproofing

$2,139,289.20

Hard Surface Finishers

NON-RESPONSIVE

 

Bidders were required to provide pricing for the base bid and alternate 1 and 2 options for a total bid cost.  Staff recommends awarding the contract, including base bid, plus alternates 1 and 2, to J. Gill & Company.

 

An Incentive Payment Plan is also included as part of this contract due to the negative impacts that limited parking can have on downtown business. The maximum payment under the Incentive Plan will be limited to $30,000, paid in $2,000 per day increments up to 15 calendar days. This amount is in addition to the prices submitted by the contractors; therefore, the amount of the award is $30,000 greater than the submitted low bid price.  

 

The work is scheduled to begin in early April with a Substantial Completion date of September 3, 2021.

 

Staff has been, and will continue, working closely with the Downtown Naperville Alliance regarding project scope and timeline.

 

FISCAL IMPACT:

CIP #: MB160

 

Central Parking Facility Maintenance Improvements are expensed to the building improvements account below.  This work is related to MB160, Downtown Parking Deck Maintenance Program, for which $1,985,000 has been budgeted in 2021.  The requested award of $1,009,526.13, which includes the maximum Incentive Payment Plan payment, is within the budgeted amount for this expense.

 

Account Number

Fund Description

Total Budget Amount

31341800-551500

Downtown Parking Fund

$1,310,100

31342300-551500

Bond

$2,289,100

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.