File #: 20-1276    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 10/22/2020 In control: City Council
On agenda: 11/17/2020 Final action:
Title: Approve the award of Option Year One to Contract 18-285, Water Meter Replacement Program, to HBK Water Meter Service, Inc. for an amount not to exceed $572,700 plus a 3% contingency and for a one-year term
Attachments: 1. Project Page (WU019), 2. Project Page (WU020)
Related files: 19-007B
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Option Year One to Contract 18-285, Water Meter Replacement Program, to HBK Water Meter Service, Inc. for an amount not to exceed $572,700 plus a 3% contingency and for a one-year term
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In January 2019, City Council approved Bid 18-285 to replace approximately 11,000 small-diameter (3/4-inch and 1-inch) water meters and reading devices located at residences throughout the City. Water meters deteriorate with age, losing accuracy as their moving parts wear out. Any meters over 16 years of age, in addition to any meters that are not compatible with AMI technology, are targeted for replacement. The term of the award was January 1, 2019 through December 31, 2020.

DISCUSSION:
HBK Water Meter Services, Inc. performed well during the original contract term. During the current term, the vendor installed approximately 7,000 residential water meters from April 2019 to December 2020. Due to the COVID-19 pandemic the vendor was not able install as many meters as planned. Approximately 6,000 3/4-inch and 1-inch water meters are currently planned for replacement from January 1, 2021 through December 31, 2021.

Due to increases in postage, insurance and prevailing wages, HBK requested a 2% increase. The requested award is the first of two optional renewals and for the term January 1, 2021 through December 31, 2021.

FISCAL IMPACT:
CIP: WU019, WU020

Water meter replacements are expensed to the infrastructure account listed below as part of the capital improvement program. A total of $1,700,000 is tentatively budgeted for replacement meters under WU020 in 2021. An additional $50,000 is also tentatively budgeted for new development meters under WU019. Both projects are pending Council approval under the 2021 Budget.

Account Number
Fund Description
Total Budget Amount
41251500-551502
Water ...