File #: 20-830    Version: 1
Type: Report Status: Agenda Ready
File created: 7/20/2020 In control: Financial Advisory Board
On agenda: 7/27/2020 Final action:
Title: Request a recommendation on the preferred funding method for the Water Automated Meter Infrastructure (AMI) project
Attachments: 1. FAB Agenda Item - 4-29-2019, 2. Water AMI Presentation - 4-29-2019
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
FINANCIAL ADVISORY BOARD AGENDA ITEM

ACTION REQUESTED:
title
Request a recommendation on the preferred funding method for the Water Automated Meter Infrastructure (AMI) project
body

DEPARTMENT: Finance Department

SUBMITTED BY: Raymond Munch, Budget Manager

BOARD/COMMISSION REVIEW:
4/29/2019 - Presented initial background to Financial Advisory Board prior to vendor selection process

BACKGROUND:
On June 18, 2019, City Council directed staff to issue a request for proposal (RFP) on implementation of an automated metering infrastructure (AMI) system for the water utility. The RFP was issued following completion of a business case analysis by West Monroe Partners, LLC, which explored the options and feasibility of implementing a new system within the utility.

On April 29, 2019, staff presented the final business case study analysis to the Financial Advisory Board with an estimate capital cost ranging between $8 and $10 million. The focus of the presentation was to determine potential funding options. The three approaches were discussed, including use of available cash within city accounts, borrowing and building the cost into the utility rates. Discussions of using cash-on-hand centered around revenues currently building in the Phosphorus Fund, which was created to assist in facility upgrades anticipated to begin in 2024.

The Water Utility ended 2019 with approximately $18.8 million in cash reserves, including $17.2 million from the Phosphorus Fund.

Unaudited Cash Balances
Fund
End of 2019
YTD (Unadjusted)
Total
Phosphorus
$ 17.24
$ 0.68
$ 17.92
Water
$ 1.55
$ 3.35
$ 4.90
Total
$ 18.79
$ 4.03
$ 22.82

The Water Utility also has approximately $23.52 million in outstanding debt service payments due over the next 10 years. After 2020, the Water Fund is scheduled to pay $17.55 million in principle and $3.61 million in interest.

Debt Service Schedule - Water Fund
Year
Principal
Interest
Total Debt Service
2020
1,566,915
796,890
2,363,805
2021
1,539,915
744,704
2,...