File #: 20-342    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 3/6/2020 In control: City Council
On agenda: 5/19/2020 Final action: 5/19/2020
Title: Approve the award of Bid 20-065, South Central Interceptor Stabilization and Hardening Project, to Earthwerks Land Improvement & Development Corporation for an amount not to exceed $886,692, plus a 3% contingency
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 20-065, South Central Interceptor Stabilization and Hardening Project, to Earthwerks Land Improvement & Development Corporation for an amount not to exceed $886,692, plus a 3% contingency
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Water Utilities owns and maintains a 2,300 foot segment of large-diameter sanitary sewer along the West Branch of the DuPage River of which the structural integrity is threatened by ongoing erosion of the east bank of the river. While the pipe is not in immediate danger, it has been a priority of Water Utilities to stop ongoing erosion and ensure the pipe is protected for the indefinite future.

For context, one stretch of the bank is eroding at a rate of one foot per year, which will expose the sanitary sewer to the river within the next several years. Another section of pipe is already exposed to the channel. Due to the extensive permitting process required for a project of this type, the project was delayed for a number of years. Now that permits have been obtained, staff believes it is imperative these issues are addressed in 2020.

The project will be constructed in phases. In March 2020, Water Utilities issued the first phase of the project, Bid 20-065, South Central Interceptor Stabilization and Hardening Project, to hire a contractor to restore a section of the riverbank. Limits of the project are Gartner Road on the north and Abrahamson Court on the south. The interceptor follows the east bank of the river; work will take place on Naperville Park District and private property.

DISCUSSION:
Advertisement Date: 03/10/2020 Notices Sent: 228
Opening Date: 04/28/2020 Planholders: 11
Proposals Received: 2

Bids were received from the following vendors:

Vendor Name
Proposed Cost
Earthwerks Land Improvement & Development
$886,692
Engineer's Es...

Click here for full text