File #: 20-013    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 1/2/2020 In control: City Council
On agenda: 3/17/2020 Final action:
Title: Approve the award of Procurement 20-123, Hot Mix Asphalt, to Arrow Road Construction, Builders Asphalt, Chicago Materials Corporation, PT Ferro, RW Dundeman and Superior Asphalt Materials for an amount not to exceed $200,000 and for a one-year term
Related files: 19-350, 21-0275
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Procurement 20-123, Hot Mix Asphalt, to Arrow Road Construction, Builders Asphalt, Chicago Materials Corporation, PT Ferro, RW Dundeman and Superior Asphalt Materials for an amount not to exceed $200,000 and for a one-year term
body

DEPARTMENT: Department of Public Works

SUBMITTED BY: Richard Dublinski, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Department of Public Works (DPW) maintains approximately 500 centerline miles of pavement, which requires the use of hot mix asphalt (HMA) to perform day-to-day maintenance and emergency repairs by DPW crews. HMA is also used as part of the Alley Improvement Program (CIP SC-223). The HMA is required to comply with the latest edition of the State of Illinois Standard specifications for hot mix asphalt material.

HMA plants typically require a minimum of 500 tons of material to be produced per day in order to operate. The total quantity that DPW typically needs for maintenance and repairs does not meet this requirement. As such, DPW is dependent upon other users requesting material and the supplier producing the correct mix in order to be able to obtain material for its HMA projects. If the HMA plant is not operating or not producing the HMA mix that DPW requires that day, DPW must call other suppliers in the area to see if they are producing the required mix.

Prior to 2019, DPW solicited bids for HMA but routinely only received one response from Chicago Materials Corporation (K-Five). In 2019, staff identified six HMA suppliers within a 35-mile radius of the City of Naperville. The identified suppliers include: Arrow Road Construction, Builders Asphalt, Chicago Materials Corporation, PT Ferro, RW Dundeman, and Superior Asphalt Materials. A 35-mile radius was chosen to offset trucking costs and HMA temperature concerns. HMA must be applied above a minimum temperature in order for it to be properly compacted.

In May 2019, the ...