CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Bid 19-275, Naper Boulevard Retaining Wall Renovations, to Lorig Construction Company for an amount not to exceed $627,800, plus a 3% contingency
body
DEPARTMENT: Transportation, Engineering and Development
SUBMITTED BY: William J. Novack, Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
Two sections of the existing timber retaining walls located along the west side of Naper Boulevard, between Chicago Avenue and the Burlington Northern Railroad Underpass, have been deteriorating over the past several years. The wall has significant deflection and requires attention before it collapses. This project (CIP #MB192) includes building a new precast retaining wall in front of existing failing wall sections.
Construction of the wall will begin in the spring of 2020 with completion anticipated by July 1, 2020. Daily lane closures will be required along the southbound lanes of Naper Boulevard adjacent to these retaining walls for the duration of the construction.
DISCUSSION:
Advertisement Date: 10/01/19 Notices Sent: 133
Opening Date: 10/24/19 Plan holders: 30
BidsReceived: 5
Bids were received from the following vendors:
Vendor |
Proposed Cost |
Engineer’s Estimate |
$541,000 |
Lorig Construction Company |
$627,800 |
Herlihy Mid-Continent Company |
$860,000 |
Alliance Contractors, Inc. |
$863,373 |
Semper Fi Land Service |
$977,000 |
Foundation Mechanics |
$1,324,000 |
The low bid was approximately 16% higher than the engineer’s estimate for the project. This increase may be related to market conditions as contractors are anticipating a large volume of upcoming work due to the recently released IDOT Capital Program.
Though the low bid is somewhat higher than anticipated, staff recommends award of the contract to Lorig Construction Company. The next lowest bidder was approximately $232,000 more than the low bid. Based on these bid results, Lorig Construction Company’s proposal represents a good value.
FISCAL IMPACT:
CIP# MB192 - Naper Boulevard Retaining Wall Renovation
The cost of the Naper Boulevard Retaining Wall Renovation is budgeted in the two accounts listed below. At total of $566,000 was allocated for this project. The additional cost identified will be financed through savings in other projects. Therefore, adequate funds are available to continue with this project.
Account Number |
Fund Description |
Total Budget Amount |
30282200-551502 |
Capital Projects Fund |
$7,913,000 |
30282200-531301 |
Capital Projects Fund |
$847,024 |