File #: 18-612    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 7/17/2018 In control: City Council
On agenda: 8/21/2018 Final action:
Title: Approve the award of Bid 18-178, 2018 Royal St George Water Main Replacement, to Copenhaver Construction, for an amount not to exceed $475,386.78, plus a 5% contingency
Attachments: 1. CIP Page
Related files: 18-844

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 18-178, 2018 Royal St George Water Main Replacement, to Copenhaver Construction, for an amount not to exceed $475,386.78, plus a 5% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     James Holzapfel, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

Supporting the City’s goal of High Performing Government to provide reliable, efficient and high-quality services to the community, in July 2018, the Water Utilities issued Bid 18-178, Royal St George Water Main Replacement.  This project seeks to replace a 900-foot segment of 10-inch watermain on Royal Saint George between Cress Creek Park and Flossmoor Court.  This segment of watermain has experienced a number of breaks disrupting utility service to the area.  Repairing the watermain will provide long lasting service and restore reliability. 

 

DISCUSSION:

 

Advertise Date:                     07/25/2018                                          Notices Sent:                                                               111

Opening Date:                     08/09/2018                                          Planholders:                                                                 16

                                                                                                                              Proposals Received:                         6

 

Bids were received from the following vendors:

 

Vendor

Bid Amount

Copenhaver Construction

$475,386.78

A Lamp Concrete Construction, Inc.

$479,050.00

Engineer’s Estimate

$479,148.00

H. Linden & Sons Sewer and Water Inc.

$493,109.00

Martam Construction, Inc.

$516,947.00

Mauro Sewer Construction

$536,815.00

Unique Plumbing Company

$616,311.25

 

Staff has experience with Copenhaver Construction and has found them to be a capable contractor. 

     

 

 

 

 

FISCAL IMPACT:

CIP #: WU04 - Water Distribution System Rehab/Replace

 

The 2018 Royal St George Water Main Replacement is expensed to the capital infrastructure account below.  A total of $1,200,000 is budgeted for project WU04 Water Distribution System - Rehabilitation/Replacement in 2018.  This water main replacement has a budget amount of $600,000.

 

Account Number

Fund Description

Total Budget Amount

430-3490-537.70-89

Water & Wastewater Fund

$10,567,500

 

*Per City directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.