File #: 18-546    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 6/28/2018 In control: City Council
On agenda: 7/17/2018 Final action:
Title: Approve the award of Bid 18-145, Grouting of Sanitary Sewer Service Connections and Service Laterals Cress Creek Phase 4, to Michels Pipe Services for an amount not to exceed $273,700, plus a 3% contingency
Related files: 19-725

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 18-145, Grouting of Sanitary Sewer Service Connections and Service Laterals Cress Creek Phase 4, to Michels Pipe Services for an amount not to exceed $273,700, plus a 3% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     James Holzapfel, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In June 2018, the Water Utilities issued Bid 18-145, Grouting of Sanitary Sewer Service Connections and Service Laterals Cress Creek Phase 4, to obtain a contractor to chemically grout 95 sanitary service laterals in the Cress Creek Subdivision. This work is part of a larger ongoing plan to rehabilitate the sanitary sewer system in the subdivision.  The goal of the sanitary sewer rehabilitation program is to improve system performance by reducing leaks from storm water runoff and groundwater infiltration (I & I). 

 

Within a year after the flooding event in April 2013, the Water Utilities Department rehabilitated 100% of the mainline sanitary sewer system and sanitary sewer laterals in the Cress Creek Subdivision.  Staff continues to work to identify sources of I & I that take up system capacity during wet weather events. 

 

Through flow monitoring and closed circuit TV inspection of the system, staff has identified significant I & I through some of the sanitary sewer laterals.  Grouting the laterals will significantly reduce the amount of ground water infiltration into the sanitary sewer system further reducing the likelihood of a basement backup or sanitary sewer overflow. 

 

The combination of sewer and lateral lining projects in the Cress Creek area have made significant improvements in the wastewater system by limiting the infiltration of groundwater and stormwater.  For example, when comparing June 2013 to June 2015, the sanitary sewers had lower flows even though there was 50% more rain.  In addition, there have been no sanitary sewer backups in Cress Creek since 2013.

 

 

DISCUSSION:

 

Advertisement Date:

06/12/2018

Notices Sent        

125

Opening Date:

06/28/2018

Plan holders:

    5

 

 

Proposals Received:        

    2

Bids were received from the following vendors:

 

Vendor Name

Proposed Fee

Michels Corporation

$273,700

Engineer’s Estimate

$300,800

National Power Rodding Corporation

$330,937.12

 

Prior to the bid opening, a No Bid response was received from a vendor explaining the construction firm was too busy.

 

This is the last phase of service connection and lateral grouting for the Cress Creek area. The completion date for this work is December 15, 2018.

 

FISCAL IMPACT:

CIP #: NA

 

This contract for lateral grouting will be expensed to the operational services account listed below. A total of $298,000 is budgeted for Cress Creek lateral grouting in 2018. The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

41251520-531308

Water & Wastewater Fund

$298,900