File #: 18-331    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 4/18/2018 In control: City Council
On agenda: 5/1/2018 Final action:
Title: Approve the award of Option Year One to Contract 17-091, Storm Sewer Rehabilitation (8"-24" Diameter) Cured-In-Place-Pipelining, to Hoerr Construction Inc. for an amount not to exceed $600,000
Attachments: 1. CIP Page
Related files: 17-342
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Option Year One to Contract 17-091, Storm Sewer Rehabilitation (8”-24” Diameter) Cured-In-Place-Pipelining, to Hoerr Construction Inc. for an amount not to exceed $600,000

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Richard Dublinski, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

Storm sewers have a functional lifespan of approximately 75 years. As a storm sewer ages, the pipe develops cracks caused by material degradation, soil settlement, root intrusion and/or adjacent construction. When a segment of storm sewer approaches the end of its useful life, the extent and severity of pipe degradation results in a high probability for pipe/system failure. Pipe failure may cause sinkholes in roadway surfaces and may also result in flooding of homes, businesses and/or public rights-of-way. The Department of Public Works has relined approximately 222,000 linear feet of storm sewers since the program began in FY2004.

 

In June 2017, the City Council approved the award of the storm sewer rehabilitation program to Hoerr Construction Inc. for a one year contract with one option year.

 

DISCUSSION:

Hoerr Construction Inc. provided excellent service during the original term of the contract and has agreed to renew the contract for an additional year with no price increases.  This rehabilitation program will improve the conductive capacity and extend the useful lifespan of the existing storm sewer system.  The scope includes cleaning and televising the storm sewer in addition to lining the storm sewers.

 

The work in 2018 includes portions of grid 82 and all of grid 96 (Brush Hill and Willow Way area), as well as single run repair sections in other grids, including a repair near Martin Avenue and Washington Street. The term of this extension is May 1, 2018 through October 15, 2018.  There are option years remaining on the contract.  

 

FISCAL IMPACT:

CIP #: SW017

 

Storm Sewer Rehabilitation is expensed to the infrastructure account below.  This work is related to SW017, Storm Sewer Lining Program, for which $600,000 has been budgeted in CY2018.  The requested award of $600,000 is within the budgeted amount for this expense.

 

Account Number

Fund Description

Total Budget Amount

31252300-551502

Bond Fund

$1,368,500