File #: 18-205    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 3/8/2018 In control: City Council
On agenda: 4/3/2018 Final action: 4/3/2018
Title: Approve the award of of Bid 18-003, 2018 Crackfilling Program, to Denler Inc. for an amount not to exceed $399,110, plus a 5% contingency
Attachments: 1. CIP Page

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of of Bid 18-003, 2018 Crackfilling Program, to Denler Inc. for an amount not to exceed $399,110, plus a 5% contingency

body

 

DEPARTMENT:                      Transportation, Engineering and Development

 

SUBMITTED BY:                     William Novack, Director

 

BOARD/COMMISSION REVIEW:
NA

 

BACKGROUND:

The Transportation, Engineering and Development Business Group issued Bid 18-003 seeking vendors to perform fiberized crackfilling on various City streets. Crackfilling consists of cleaning and sealing of any cracks, voids or joints 2” in width or less with asphalt cement reinforced by polypropylene fibers.  It is a cost effective preventative maintenance technique and performed routinely can keep water and debris from getting into pavement.

 

DISCUSSION

Advertisement Date:

3/01/18

Notices Sent:

106

Opening Date:

3/16/18

Planholders:

   6

 

 

Proposals Received:

   2

 

Bids were received from the following vendors:

 

Company Name

Proposed Fee

Denler Inc.

$399,110.00

SKC Construction Inc.

$401,260.00

Engineer’s Estimate

$450,250.00

 

The engineer’s estimate is based on prices from the 2017 Crackfilling Program, which received bids in March 2017.  The cost difference is likely attributed to the fact that larger agencies such as the Illinois Department of Transportation have smaller capital programs this year, which results in more competitive pricing for the City. 

 

 

 

 

 

 

 

 

 

 

 

FISCAL IMPACT:

CIP#: MP009 - Street Maintenance Improvement Program (MIP)

 

The MIP is expensed to the following accounts listed below.  A total of $10.5 million has been budgeted for the MIP in 2018.  The requested amount is within budget.

 

Account Number

Fund Description

Total Budget Amount

30282400 - 551502

Road and Bridge Fund

$2,239,885

30282200 - 551502

Capital Projects Fund

$5,468,115

30282500 - 551502

Motor Fuel Tax Fund

$3,820,000

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.

 

This award of $399,110 for Crackfilling is one component of the overall award for MP009.  The chart below breaks out the different award components and award timeframes for the MIP.

 

Project Name

Bid No.

Award Amount

Status

Resurfacing - MFT

18-001

$3,048,323.50

Recommend for award - 4/3/2018

Resurfacing - City

18-002

$3,025,538.50

Recommend for award - 4/3/2018

Crackfilling

18-003

$399,110.00

Recommend for award - 4/3/2018

Patching

18-004

$397,400.00

Recommend for award - 4/3/2018

Microsurfacing

18-005

$1,578,455.00

Recommend for award - 4/3/2018

Sidewalk R&R

18-006

$266,423.50

Recommend for award - 4/3/2018

Total

 

$8,715,250.50