File #: 17-793    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 10/10/2017 In control: City Council
On agenda: 11/7/2017 Final action: 11/7/2017
Title: Accept the Record of Emergency Award of Procurement 17-213, Uninterruptable Power Supply, to Volt Electric for an amount not to exceed $36,397.
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Accept the Record of Emergency Award of Procurement 17-213, Uninterruptable Power Supply, to Volt Electric for an amount not to exceed $36,397.
body

DEPARTMENT: Department of Public Works

SUBMITTED BY: Richard Dublinski, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Department of Public Works - Public Building Operations (DPW-PBO) was notified on September 22, 2017 that the uninterruptable power supply (UPS) at the Municipal Center went into "trouble" mode. PBO staff requested the City's contracted vendor, United Power, to work through the issue. During a diagnostic exercise, the unit failed and brought down the data center (including all programs supported through IT) and communications (computers and phones) at the Municipal Center.

During an attempt at a repair, the United Power technician replaced a board in the unit. When the unit was brought back online, the IGBT's (specialized transistors) blew, the new board fried and the unit started to smoke. The unit is 18 years old and has been kept in service with used parts. Replacement parts are no longer manufactured. A typical unit has a life expectancy of twelve years. United Power strongly recommended the UPS be replaced.

DISCUSSION:
The emergency procurement was approved by the Chief Procurement Officer on September 27, 2018, per Section 1-9B-4:6 Emergency Procurements, of the Naperville Procurement Code.

Since a UPS failure causes a significate impact to all IT programs, it was critical that the system be replaced in a short period of time. PBO provided the scope of work to five contractors and requested a quote for the work.

The following quotes were received:

Vendor
Quote
Delivery
Installation/Disposal Included
Volt Electric*
$36,397
1 Week
Yes
CDW-G
$45,516.22
4-6 Weeks
Yes
Nationwide Power
$22,188
4 Weeks
No
United Power & Battery
$30,450
3 Weeks
No
Vertiv
$21,203.35
4-6 Weeks
No
*Note that Volt's unit price was price matc...

Click here for full text