File #: 17-743    Version: 1
Type: Change Order & Work Order Status: Passed
File created: In control: City Council
On agenda: 11/7/2017 Final action: 11/7/2017
Title: Approve the Award of Change Order #1 to Option Year Two of Contract 15-122, Excavation and Underground Utility Repairs, to Western Utility LLC for an amount not to exceed $50,000 and a total award of $166,953.
Attachments: 1. 15-122 Prior Awards.pdf, 2. Project Page - WWU06.pdf, 3. Project Page - WU04.pdf

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the Award of Change Order #1 to Option Year Two of Contract 15-122, Excavation and Underground Utility Repairs, to Western Utility LLC for an amount not to exceed $50,000 and a total award of $166,953.

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     James Holzapfel, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On October 18, 2014, City Council awarded Contract 15-122, Excavation and Underground Utility Repairs, to Western Utility LLC for an amount not to exceed $116,953 to excavate and repair underground water and wastewater utility infrastructures. The Water Utilities uses this contract to respond to emergencies when in-house resources are not available and for planned work that cannot be accomplished without diverting in-house resources from other high-priority work.  City Council approved Option Year 1 on October 20, 2015 and Option Year 2 on November 1, 2016. Each of the two option year awards were for an amount not to exceed $116,953.

 

The current contract term expires December 31, 2017, with no renewal options remaining.

 

DISCUSSION:

The Water Utilities has recently assigned three water main breaks to the contractor resulting in an unplanned expense of approximately $25,000. Additionally, there were unforeseen complications on a planned water main replacement assigned to Western Utility, resulting in an additional $6,000 expense. The requested $50,000 change order will allow outstanding invoices to be paid and provide a reserve of approximately $19,000 to respond to emergencies such as water main breaks that would require repair prior to the end of the contract term on December 31, 2017. 

 

FISCAL IMPACT:

CIP #: WU04, WWU06

 

Excavation and underground utility repairs are expensed to the capital improvement program and building repair and maintenance service accounts listed below. A total of $4,717,500 is budgeted for underground work in the Water and Wastewater Utility in CY2017.  The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

430-3490-537.70-89

Water & Wastewater

$8,852,500

430-3913-537.40-34

Water & Wastewater

$68,000