Title: Approve the Award of Bid 17-028, Raymond Drive Interceptor Sewer - Phase 4, to Michels Pipe Services for an amount not to exceed $668,661, plus a 3% contingency.
Attachments: 1. Project Page - WWU06.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the Award of Bid 17-028, Raymond Drive Interceptor Sewer - Phase 4, to Michels Pipe Services for an amount not to exceed $668,661, plus a 3% contingency.

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Jim Holzapfel, Water Utilities Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Water Utilities issued Bid 17-028 seeking a contractor for the rehabilitation of existing sanitary sewer pipelines by installing glass reinforced plastic cured-in-place thermosetting resin pipe cured with ultraviolet (UV) light.  This new process was specified because it is safer, has less impact on the environment and provides a product that is stronger and more flexible than heat Cured-in-Place-Pipelining (CIPP) that the City has historically used.  Recently, the City successfully installed UV-cured liners in small-diameter applications.  This will be the first large-diameter lining project utilizing this product.

 

DISCUSSION:

Advertisement Date:   5/03/2017                                                               Notices Sent:                       238

Opening Date:                        5/19/2017                                                               Planholders:   19

                                                                                                                                                   Bids Received: 3                                          

BID TABULATION

The following bids were received:

 

COMPANY

BID AMOUNT

Michels Pipe Services

$668,661

Engineer’s Estimate

$857,350

Layne Inliner, LLC

$887,003

J.C. Dillon

$929,046

 

The Engineer’s Estimate for this project was based on an average historic bid unit price of $365 per linear foot for the traditional CIPP lining and budgetary quotes from vendors, plus $14,000 per manhole. Since Naperville has not previously completed any large-diameter lining with UV-Cured CIPP.  The Engineer’s project estimate is significantly higher than the low bidder’s project proposal, but in line with the other bidders. 

 

Michels Pipe Services is experienced with installing UV-cured CIPP. 

 

FISCAL IMPACT:

CIP #: WWU06

 

WWU06 - Sanitary Sewer System Rehab/Replacement - Interceptors/Trunk

WWU06 is an annual project in the Utility’s Capital Improvement program that investigates and rehabilitates deteriorated sanitary interceptor, trunk, mainline and service lateral sewers.  The project uses various trenchless technology processes and focuses on areas known to have significant groundwater infiltration.

 

Sanitary sewer rehabilitation and replacements are expensed to the capital improvement account listed below. A total of $3,632,500 is budgeted for WWU06 in CY2017.  The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

430-3490-537.70-89

Water and Wastewater

$8,852,500

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.