Approve the award of Bid 25-289, 2025 New Sidewalk Improvements Program, to Triggi Construction, Inc. for an amount not to exceed $309,343 plus a 5% contingency
body
DEPARTMENT: Transportation, Engineering and Development
SUBMITTED BY: Jennifer Louden, Director of TED
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
In 2022 and 2023, the Transportation Advisory Board (TAB) and City Council approved a three-year New Sidewalk Program, whose purpose is to improve walkability throughout the City. The first year of this program was constructed in 2023. This award is for year three.
In September 2025, the Transportation, Engineering and Development Business Group (TED) issued Bid 25-289, 2025 New Sidewalk Improvements Program, to conduct work that consists of sidewalks, driveways, curb and gutter, tree pruning, tree relocation, excavation, sodding, erosion control, mobilization, brick pavers, modular block retaining walls, traffic control, and other incidental and miscellaneous items of work per the plans, standard specifications, and special provisions. This project includes the following locations:
* Villa Ave and Wright St (northeast corner)
* 10th Ave (north side), Webster St to Main St
* 11th Ave (north side), Main St to Washington St
* 12th Ave (north side), Main St to Washington St
* 14th Ave (south side), Eagle St to Main St
* Main St (west side), 11th Ave to 14th Ave
* Webster St (east side), 10th Ave to 11th Ave
* Webster St (east side), 12th Ave to 14th Ave
DISCUSSION:
Advertisement Date:
09/18/2025
Notices Sent:
207
Opening Date:
10/09/2025
Plan holders:
24
Proposals Received:|10 10|
Bids were received from the following vendors:
Vendor Name
Proposed Cost
Triggi Construction, Inc.
$309,343.00
Everlast Blacktop
$341,673.66
Miller Pipeline, LLC
$362,852.70
Schroeder & Schroeder, Inc.
$397,700.00
Engineer's Estimate
$408,770.78
Alliance Contractors, Inc.
$428,606.23
G&M Cement Construction, Inc.
$434,227.53
...