Title: Approve the award of Change Order #1 to Contract 26-032 Municipal Center IT Server Room Expansion, to Lite Construction, Inc. for an additional 5 months  
Related files: 26-0313
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 26-032 Municipal Center IT Server Room Expansion, to Lite Construction, Inc. for an additional 5 months 

body

 

DEPARTMENT:                     Information Technology

 

SUBMITTED BY:                     Jacqueline Nguyen, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The City Council awarded contract 26-032 Municipal Center IT Server Room Expansion to Lite Construction, Inc. on March 18, 2026, with a completion date of December 15, 2026.  The purpose of this contract is to expand the IT server room for capacity expansion and long-term scalability.

 

DISCUSSION:

This change order is requested to extend the contract completion date to allow sufficient time to complete the remaining project work. The project schedule was impacted by several unforeseen circumstances, including a delayed project start, modifications to the fire suppression system, and delays in installing the new generator unit. Furthermore, due to the premature failure of the existing cooling unit, installation of the new computer room air conditioning (CRAC) units had to be prioritized to maintain cooling operations within the data center. The CRAC units remain under monitoring to ensure proper operation and performance.

 

These circumstances have affected the sequencing and completion of scheduled construction work, requiring additional time. The extension will allow the contractor to complete all work, conduct necessary testing and commissioning, and make sure all systems are fully operational before closeout. The anticipated new completion date of the IT server room expansion project is May 15, 2027.

 

FISCAL IMPACT:

CIP #: CE164

 

The requested Change Order is for an extension of time only and does not increase the value of the contract.