Legislation Details

File #: 26-0557    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 4/21/2026 In control: City Council
On agenda: 5/5/2026 Final action:
Title: Approve the award of Bid 26-035, Mill Street Lighting Project, to Utility Dynamics Corporation for an amount not to exceed $380,770 plus a 5% contingency
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 26-035, Mill Street Lighting Project, to Utility Dynamics Corporation for an amount not to exceed $380,770 plus a 5% contingency
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: Jennifer Louden, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Electric Utility ("Utility") announced plans to remove the utility poles along the west side of Mill Street from Ogden Avenue to Bauer Road and install underground electrical lines. These poles currently support and power the streetlights on Mill Street. As such, the Transportation, Engineering and Development (TED) Business Group is planning, in coordination with the Utility project, to upgrade the street lighting to meet current standards.

The final product will provide nighttime friendly lighting consistent with LEED goals and Green Globe criteria for light pollution reduction.

In March 2026, TED issued Bid 26-035, Mill Street Lighting Project to replace the street lighting along Mill Street.

DISCUSSION:

Advertisement Date:
3/30/2026
Notices Sent:
2958
Opening Date:
4/20/2026
Planholders:
35


Proposals Received:|1010|
Bids were received from the following vendors:

Vendor Name
Proposed Cost
Engineer's Estimate
$346,905.00
Utility Dynamics Corporation
$380,770.00
HEI Utility Contractors
$440,426.50
DND Electric, Inc.
$683,091.30

The low bid is approximately 10% above the engineer's estimate. This is primarily attributable to higher-than-anticipated parkway restoration costs, which are necessary for the completion of the project and will be carefully monitored during construction.

Staff recommends award of the contract to Utility Dynamics Corporation as the lowest responsive and responsible bidder for the procurement of construction services, as defined by Section 1-9B-7 of the Procurement Code (RBO-qualified).

The contractor is afforded 150 calendar days to complete the work following execution of...