File #: 24-0786    Version: 1
Type: Procurement Award Status: Passed
File created: 6/25/2024 In control: City Council
On agenda: 7/16/2024 Final action: 7/16/2024
Title: Approve the award of JOC Procurement 19-13.2-G.00-DPW, Commercial Overhead and Pedestrian Door Replacements, to Robe Construction, Inc., for an amount not to exceed $112,004.24 plus a 5% contingency
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of JOC Procurement 19-13.2-G.00-DPW, Commercial Overhead and Pedestrian Door Replacements, to Robe Construction, Inc., for an amount not to exceed $112,004.24 plus a 5% contingency
body

DEPARTMENT: Department of Public Works

SUBMITTED BY: Richard Dublinski, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Department of Public Works - Public Building Operation (DPW-PBO) is responsible for the maintenance of 57 buildings including the operation of commercial garage doors (overhead and four-fold), pedestrian doors, and motorized security gates and dock lifts. Capital Improvement Project (CIP) MB188, Municipal Facility Window and Door Replacement, was established to replace these types of assets as they fail due to age, weather, and heavy usage.

DPW-PBO worked with the City's JOC contractor, Robe Construction, Inc., to develop solutions to replace the overhead, pedestrian and dock lift replacements outlined in the discussion.

DISCUSSION:
The projects listed below have been identified by DPW-PBO and will be installed as part of CIP MB188 in 2024.

1. Replace two exterior metal pedestrian doors at Fire Station 10 ($12,810)
2. Replace five overhead sectional doors at the Department of Public Utilities - Water (DPU-W) North Operations Center ($47,700)
3. Replace three exterior metal pedestrian doors at the Department of Public Utilities - Electric (DPU-E) Service Center ($29,100)
4. Replace the single exterior metal pedestrian door with a double door at the DPU-E Washington Street Substation ($12,300)
5. Replace the dock lift at the DPU-E Electric Service Center Garage ($10,094.24)

The anticipated completion date of the project is December 13, 2024.

FISCAL IMPACT:
CIP #: MB188

Commercial Overhead and Pedestrian Door Replacements are expensed to the Building Improvements accounts below. The work is related to MB188, Municipal Facility Window and Door Replacement, for which $370,000 had b...