File #: 23-1315    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 11/13/2023 In control: City Council
On agenda: 12/5/2023 Final action:
Title: Approve the award of Change Order #1 to Bid 22-306, Municipal Entry Door Replacement, to Allied Door, Inc. for an additional 122 days
Related files: 22-1423

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Bid 22-306, Municipal Entry Door Replacement, to Allied Door, Inc. for an additional 122 days

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Richard Dublinski, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On December 7, 2022, the City Council awarded Bid 22-306 to Allied Door, Inc. to replace the sliding entry doors at the Municipal Center due to age, parts obsolescence, and the frequent need for maintenance and repairs resulting from high volume use and changing weather conditions.

 

The contract was awarded for $79,823, plus a 5% contingency with a completion date of August 31, 2023.

 

DISCUSSION:

Due to manufacturing delays, Allied Door, Inc. did not receive the doors until October 2023. 

 

A Change Order is requested to extend the contract by 122 days to allow Allied Door, Inc. to complete the work. If approved, the revised completion date will be December 31, 2023.

 

No additional funds are needed to complete the work.

 

FISCAL IMPACT:

CIP #: MB222

 

The work is related to MB222, Municipal Center Improvements. The additional time requested on the contract will not add additional expense to the award amount.