Title: Receive the Springbrook Water Reclamation Center Capital Improvement Summary Report
Attachments: 1. SWRC Project Timeline_Budget2026
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PUBLIC UTILITIES ADVISORY BOARD AGENDA ITEM

ACTION REQUESTED:
title
Receive the Springbrook Water Reclamation Center Capital Improvement Summary Report
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director Water Utilities

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Springbrook Water Reclamation Center (SWRC) is currently undergoing significant upgrades driven by three primary factors: regulatory compliance, specifically regarding nutrient removal (phosphorus); the need to replace aging critical infrastructure; and the necessity to expand treatment capacity to meet long-term demands.

The 2026 Capital Improvement Program reflects a strategic investment in these areas. Key initiatives focus on modernizing electrical distribution, enhancing biosolids handling, and upgrading both North and South Plant processes to ensure environmental compliance and operational reliability.

DISCUSSION:
The following capital improvement projects are budgeted for execution or continuation in 2026. The table and summaries below detail the scope, the specific 2026 budget allocation, and the estimated completion date for each project.
Project Title
2026 Budget
Est. Completion
Electrical Distribution System Improvements
$625,000
Dec 31, 2026
Biosolids Holding Tank - Phase 2
$1,914,000
Dec 31, 2026
South Plant RAS/Grit Improvements
$7,412,000
Dec 31, 2026
South Plant Capacity Upgrades & Improvements
$20,359,550
Dec 31, 2028
Nutrient Removal & North Plant Aeration
$1,775,000
Dec 31, 2029
Cloth Media Disc Filter Facilities
$1,900,000
Dec 31, 2030
1. SWRC - Electrical Distribution System Improvements
* Scope: Installation of a second electrical feed to the SWRC as required by the Illinois EPA and replacement of original direct-bury cables and aging transformers to meet current standards.
* 2026 Activity: Complete construction and maintenance upgrades.
* Overall Timeline: Completion anticipated by December 31, 2026.
2. SWRC - Biosolids Hol...