File #: 25-1356    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 10/13/2025 In control: City Council
On agenda: 11/4/2025 Final action:
Title: Approve the award of Change Order #1 to Cooperative Procurement 25-114, Northwest Water Works Exterior Wall and Roof Restoration, to Garland/DBS, Inc. for the amount not to exceed $21,596 and a total award of $813,014
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Cooperative Procurement 25-114, Northwest Water Works Exterior Wall and Roof Restoration, to Garland/DBS, Inc. for the amount not to exceed $21,596 and a total award of $813,014

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The City Council awarded Cooperative Procurement 25-114 to Garland/DBS, Inc. on April 4, 2025, for the amount of $791,418 for the restoration of the roof and exterior walls at Northwest Water Works.

 

DISCUSSION:

During the removal of the existing roof membrane, it was discovered that both layers of roof insulation were water damaged and in need of replacement before the new roof membrane could be installed. This Change Order is requested to cover the additional cost of $21,596 for the unexpected roof insulation damage, removal, and replacement.

 

FISCAL IMPACT:

CIP #: WU060 - Elevated Tank and Water Reservoir Coating

 

Repairs to Northwest Water Works are expensed to the Infrastructure account listed below. The 2025 budget allocated $2.5 million for this project as part of the Water Capital Improvement Program. The requested change order of $21,596 can be accommodated within the budget.

 

Account Number

Fund Description

Total Budget

41251500-551502

Water Utilities

$68,654,488