File #: 22-1124    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 9/12/2022 In control: City Manager Procurement Awards
On agenda: 10/1/2022 Final action:
Title: Approve the award of Change Order #14 to Contract 16-015, ERP Software and Implementation, to Tyler Technologies to add additional scope
Related files: 20-402, 22-0566, 22-0990, 23-1215
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY MANAGER AUTHORITY PROCUREMENT AWARDS

 

ACTION REQUESTED:
title

Approve the award of Change Order #14 to Contract 16-015, ERP Software and Implementation, to Tyler Technologies to add additional scope

body

 

DEPARTMENT:                     Finance Department

 

SUBMITTED BY:                     Rachel Mayer, Finance Director

 

BACKGROUND:

The City Council awarded Contract 16-015 to Tyler Technologies on November 15, 2016 for the purchase and implementation of a new ERP system, which is comprised of three software:

                     Enterprise ERP (fka Munis)

                     Enterprise Permitting and Licensing (EPL fka EnerGov)

                     Cashiering

 

Of the three software, only EPL has a significant amount of implementation left to complete and there are no additional EPL implementation hours remaining on the contract. 

 

DISCUSSION:

The purpose of this change order is to add project management and implementation services for the EPL implementation through the end of the current contract term (12/31/2023).  The cost is $92,000; however, this change order will not result in an increase in the contract award amount because the costs will be offset by unused implementation hours in Enterprise ERP and Cashiering. 

 

It is anticipated that EPL will go-live in a phased approach.  The schedule below focuses on implementations over the next 12 months. 

                     Residential permits: November 2022

                     Commercial permits: Spring 2023

                     Inspections: Summer 2023

                     Plan application review: Fall 2023

 

Additional implementation phases for late 2023 and 2024 will be scheduled in 2023 after the first implementations have been completed.

 

Staff evaluated whether we could complete the EPL implementation without additional hours and determined that assistance was needed from Tyler.  However, the number of hours is limited.  Staff is requesting 1.5 days/month of project manager assistance and 2 days of implementer assitance per month through the end of the contract term.    

 

FISCAL IMPACT:

This change has no fiscal impact as it is only adding scope.