File #: 17-805    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 10/20/2017 In control: City Council
On agenda: 11/7/2017 Final action: 11/7/2017
Title: Approve the Award of Bid 17-190, Green Acres Water Main Improvements, to Performance Construction & Engineering for an amount not to exceed $216,495, plus a 5% contingency.
Attachments: 1. Project Page - WU10.pdf
Related files: 17-719, 17-941
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the Award of Bid 17-190, Green Acres Water Main Improvements, to Performance Construction & Engineering for an amount not to exceed $216,495, plus a 5% contingency.
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Jim Holzapfel, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
On September 19, 2017, the City Council adopted a resolution to approve the execution of an agreement between the City of Naperville and the Naperville Fire Protection District (District). The agreement provides that in exchange for the City's installing and maintaining water main improvements in the Green Acres Subdivision of the District, the District will contribute $650,000 towards the City's acquisition of a new fire truck.

The Water Utilities issued Bid 17-190 seeking a vendor to complete improvements to install water main to provide fire protection to the Green Acres subdivision. The project consists of installing 1,425 lineal feet of 12-inch water main from West Street through Sportsman's Park to Green Acres Drive and terminating with a fire hydrant.

DISCUSSION:
Advertisement Date:
09/27/17
Notices Sent:
349
Opening Date:
10/18/17
Planholders:
22


Proposals Received:
8

Company Name
Proposed Fee
Performance Construction & Engineering
$216,495.00
Swallow Construction Corporation
$223,783.00
Len Cox & Sons Excavating
$227,539.00
Maneval Construction
$237,268.20
A Lamp Concrete Contractors, Inc.
$239,910.00
Sheridan Plumbing & Sewer Inc.
$254,565.00
Copenhaver Construction
$258,829.00
Engineer's Estimate
$304,940.00
Bisping Construction
$367,699.00

The Engineer's Estimate was based on historic bid information received over the past three (3) years for water main work within the City of Naperville. The prices for Bid 17-190 were less than what staff anticipated due to fewer conflicts with other underground utilities.

FISCAL IMPACT:
CIP#: WU10

Water main improvements are expensed to the capital improvement pro...