Two projects on or adjacent to the Riverwalk are currently in progress:
• Eagle Street Gateway
• Fredenhagen Park Fountain Repairs
A status update for each project is provided below:
DISCUSSION:
Eagle Street Gateway
Construction on the Gateway project is complete. A grand opening celebration is scheduled for Friday, November 14th at 3:30 p.m.
Fredenhagen Park Fountain Repairs
The contractor has completed their scope of work. The fountain was tested briefly and will now be winterized.