File #: 20-1067    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 9/10/2020 In control: City Manager Procurement Awards
On agenda: 10/1/2020 Final action:
Title: Approve the award of Change Order #1 to Contract 20-009, 2020 Sidewalk and Curb Maintenance Program, to AC Concrete Construction for an amount not to exceed $6,236.19 and a total award of $653,418.69
Related files: 20-375, 20-387, 20-1380
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CHIEF PROCUREMENT OFFICER AUTHORITY PROCUREMENT AWARDS

ACTION REQUESTED:
title
Approve the award of Change Order #1 to Contract 20-009, 2020 Sidewalk and Curb Maintenance Program, to AC Concrete Construction for an amount not to exceed $6,236.19 and a total award of $653,418.69
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BACKGROUND:
The City Council awarded Contract 20-009 to AC Concrete on April 21, 2020 with a completion date of July 30, 2020. The purpose of this contract is to remove and replace sidewalk, roll curb and gutter, barrier curb and gutter and concrete and asphalt driveway aprons at locations throughout the City.

This is the first change order to this contract. No previous change order or extensions have been approved.

DISCUSSION:
Change Order #1 & Partial balances as built quantities as recorded in the City's SASIE database through substantial completion of the project and anticipated quantities to complete job as directed in the contract documents.

The amount of this change order exceeds the original contract amount by $6,236.19, 0.96% and by 0 days.

This contract was approved with contingency in the amount of 3% ($19,415.48) of the original contract value and 29 days. Staff requests the use of contingency funds for the change order.

Contract Award
Original Contract Value
$647,182.50
Prior Cumulative Approved Change Orders
$0.00
Subtotal
$647,182.50
(+/-) This Change Order
$6,236.19
Total Contract Value
$653,418.69

Contingency
Authorized Contingency
Days
Dollars
Original Amount
29
$19,415.48
(-) Previously Authorized

$0.00
Subtotal

$19,415.48
(-) This Change

$6,236.19
Balance Left
29
$13,179.28


FISCAL IMPACT:
CIP #: MP004 - Sidewalk Maintenance

The change order required the requested adjustment to the following accounts. The requested change order is within the budgeted amount for this expense.

Account Number
Fund Description
Amount
30282200-551502
Capital Projects F...

Click here for full text