File #: 23-0374    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 3/23/2023 In control: City Council
On agenda: 4/5/2023 Final action: 4/5/2023
Title: Approve the award of Bid 23-016, 2023 Sanitary Sewer Service Lateral Lining and Vac-A-Tee Installation, to Performance Pipelining, Inc. for an amount not to exceed $1,949,995 plus a 3% contingency
Related files: 23-1138
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 23-016, 2023 Sanitary Sewer Service Lateral Lining and Vac-A-Tee Installation, to Performance Pipelining, Inc. for an amount not to exceed $1,949,995 plus a 3% contingency
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In February 2023, the City issued Bid 23-016 for rehabilitation of approximately 169 existing sanitary sewer service laterals by utilizing the installation of cured-in-place pipe (CIPP). The bid also includes the installation of approximately 200 Vac-A-Tee cleanouts. All Vac-A-Tee cleanouts will be installed in Brookdale Subdivision to facilitate sewer lateral line grouting, which will reduce groundwater infiltration.

Lining and/or grouting service laterals has shown to be effective in reducing groundwater and rainfall related infiltration and inflow into the sanitary sewer system. Excessive infiltration and inflow into the sanitary sewer system take up system conveyance capacity which may cause sanitary sewer overflows and sanitary sewer basement backups.

The Sanitary Sewer Service Lateral Lining and Vac-A-Tee program is part of the City's IEPA required ten-year wastewater collection rehabilitation plan, as well as the IEPA required ten-year infiltration and inflow reduction plan to reduce wastewater backups during heavy rain events.

DISCUSSION:
Advertisement Date: 02/28/2023
Opening Date: 03/16/2023 Notices Sent: 202
Plan holders: 15
Proposals Received: 2

BID TABULATION:
The following bids were received.

Vendor Name
Proposed Cost
Engineer's Estimate
$1,920,560
Performance Pipelining
$1,949,995
Hoerr Construction
$2,194,300

The term of the contract is from the date of award through December 31, 2023, with four one-year options to ex...