CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Bid 22-017, Grouting of Sanitary Sewer Service Connections and Service Laterals - Cress Creek Phase 8, to Michels Corporation for an amount not to exceed $219,800 plus a 5% contingency
body
DEPARTMENT: Water Utilities
SUBMITTED BY: Darrell Blenniss, Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
After the April 2013 flooding event, the Water Utilities rehabilitated all mainline sanitary sewer and manholes in the Cress Creek subdivision. The combination of sewer main and sewer lateral rehabilitation projects in Cress Creek made significant improvements in the wastewater system by limiting the infiltration of groundwater and stormwater. The Utility continues to identify sources of inflow and infiltration (I & I) taking up system capacity during wet weather events.
Through flow monitoring and closed-circuit televising inspection of the system, staff identified significant I & I through some sanitary sewer laterals. Grouting laterals will significantly reduce the amount of groundwater into the sanitary sewer system further reducing the likelihood of basement backups or sanitary sewer overflow.
In February 2022, the Water Utilities issued Bid 22-017, 2022 Grouting of Sanitary Sewer Services Connections and Service Laterals - Cress Creek Phase 8. The work includes testing and grouting of 44 six-inch diameter sanitary sewer service laterals in the Cress Creek subdivision. The lateral grouting program is part of the City's ten-year Infiltration and Inflow Reduction Program required and registered with the Illinois Environmental Protection Agency (IEPA).
DISCUSSION:
Advertisement Date: 2/03/2022 Notices Sent: 203
Bid Opening Date: 2/18/2022 Planholders: 10
Proposals Received: 3
Vendors Name
Proposed Cost
Engineers Estimate
$211,925
Michels Corporation
$219,800
Visu-sewer Clean & Seal, Inc.
$229,175
National Power Rodding Corporation
$341,600
...
Click here for full text