Title: Approve the award of Bid 25-255, Ogden Avenue Phase II Water Main Improvements, to Trine Construction Corporation for an amount not to exceed $4,019,300 plus a 3% contingency
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 25-255, Ogden Avenue Phase II Water Main Improvements, to Trine Construction Corporation for an amount not to exceed $4,019,300 plus a 3% contingency
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In support of the City's priority to provide utility services that are reliable and safe, in November 2025, the Water Utilities issued Bid 25-255, Ogden Avenue Phase II Water Main Improvements. The project includes the replacement of the water main on Ogden Avenue from 1,000 feet west of Mill Street to Washington Street.

The purpose of the project is to replace aging and deficient water main on Ogden Avenue. The existing six-inch and ten-inch cast iron water main installed in the 1940s and 1960s will be replaced and upsized to 16-inch PVC pipe in accordance with City standards.

DISCUSSION:

Advertisement Date:
11/18/2025
Notices Sent:
434
Opening Date:
12/18/2025
Plan holders:
61


Proposals Received:|1010|
Bids were received from the following vendors:

Vendor Name
Base Bid
Trine Construction Corporation
$4,019,300.00
Acqua Contractors Corporation
$4,490,000.00
Performance Construction and Engineering
$4,989,888.00
Engineer's Estimate
$2,678,111.00

Trine Construction Corporation submitted the low bid for the project at $4,019,300. The bid is 63% higher than the budgeted amount of $2,460,000. Water Utilities staff based the 2026 budget on the average per-foot cost of similar projects in 2025.

Staff spoke with the low bidder and was informed that pricing is being driven by the nature of the work, location of the project on Ogden Avenue, and the complexities related to the installation of large-diameter fusible PVC piping.

While costs are greater than anticipated, it is not in the best interest of the City to cancel, delay, or re-bid the project. Staff anticipates that the factors driving higher costs will continu...