File #: 23-0988    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 8/23/2023 In control: City Council
On agenda: 10/3/2023 Final action: 10/3/2023
Title: Approve the award of Cooperative Procurement 23-133, In-ground Structures, to Wesco for an amount not to exceed $1,498,100 and for a one-year
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Cooperative Procurement 23-133, In-ground Structures, to Wesco for an amount not to exceed $1,498,100 and for a one-year
body

DEPARTMENT: Electric Utility

SUBMITTED BY: Brian Groth, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Electric Utility (Utility) installs and maintains transformers and switchgear throughout the City as vital equipment for the electric grid. Vaults are placed in the ground, provide structural support for the equipment, and allow cables to be run and connected to the transformers and switchgear. Handholes are also required to allow access to the underground cable for installation and splicing purposes. These "boxes" are purchased as a complete structure from suppliers.

Vaults and handholes are installed at the time of construction and are replaced due to aging or damage as needed. As part of the Utility's ongoing asset management program, inspections of these structures have identified several vaults and handholes that are damaged or failing and are in need of urgent replacement.

DISCUSSION:
The Utility warehouse purchases these structures throughout the year for both new construction projects and to replace damaged or failing structures that have reached end of useful life.

This request represents the estimated number of devices that the Utility requires to support its operations over the next 12 months. As with all other material the warehouse purchases, these items have seen significant cost increases in the past few years and lead times have increased. As such, staff recommends placing larger orders at one time to secure the needed material and not be impacted by installation schedules.

Staff has identified an approved cooperative contract, Sourcewell Cooperative Contract 091422-WES through Wesco, for the procurement of the underground structures. Purchase and delivery of these items will occur as needed through the next 12 months.

The term ...

Click here for full text