File #: 17-852    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 11/13/2017 In control: City Council
On agenda: 12/5/2017 Final action: 12/5/2017
Title: Approve the Award of Bid 17-191, Southeast Water Works Booster Pump Upgrades, to Brieser Construction for an amount not to exceed $313,700, plus a 5% contingency.
Attachments: 1. Project Page - WU32.pdf
Related files: 20-515, 18-566
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the Award of Bid 17-191, Southeast Water Works Booster Pump Upgrades, to Brieser Construction for an amount not to exceed $313,700, plus a 5% contingency.
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Jim Holzapfel. Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The Water Utilities issued Bid 17-191 seeking vendors to replace two of three existing water booster pumps and upgrade associated electrical equipment for the Southeast Water Works.

The Southeast Water Works initially constructed in 1980 with three booster pumps, and a three-million-gallon underground reservoir attached the City's ground water supply (wells). In 1986, the station underwent an upgrade adding an additional three million gallons of reservoir capacity (for a total of six million gallons). The station underwent a final change in 1991 with modifications to receive Lake Michigan water from the DuPage Water Commission.

The booster pumps pump water from the site's underground six-million-gallon potable water reservoir into the water distribution system to maintain system pressure and provide water during periods of high demand and emergency fire flows.

Recently, one of the three pumps suffered a catastrophic failure where repairing the pump is not feasible. Additionally, one of the two remaining pumps is demonstrating problems (overheating) and after evaluation staff determined it is near failure and recommends it also be replaced.

All three pumps are at the end of their economic life and replacement is the most economical alternate to restore pumping capacity and ensure system reliability. The bid proposes to replace two of the three pumps. The replacement of the last pump will take place when it begins to show signs of failure.

DISCUSSION:
Advertisement Date:
10/23/17
Notices Sent:
109
Opening Date:
11/13/17
Planholders:
17


Proposals Received:
4
The following were received

Company Name
Proposed Fee
E...