CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Cooperative Procurement 25-231, Police Department Air Handler Unit 3 Replacement, to Carrier Corporation for an amount not to exceed $157,460
body
DEPARTMENT: Department of Public Works
SUBMITTED BY: Richard Dublinski, Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
The Department of Public Works - Public Building Operation (DPW-PBO) is responsible for the maintenance and operation of the Carrier brand chiller and air handling units associated with the heating and cooling systems at the Police Department.
Per the American Society of Heating, Refrigeration and Air-Conditioning Engineers, chillers and air handling units have a life expectancy of 25 years. The system at the Police Department is approaching 36 years old. However, through prescribed maintenance and a phased approach to replace system components, the City has, and can continue to, prolong the life of the equipment, maximize energy savings, and lower operating costs.
DISCUSSION:
In May 2023, Pure Air Control Services, a division of Weatherproofing Technologies, Inc., provided an inspection of the air handling units at the Police Department and Municipal Center and developed a five-year plan for maintenance and replacements. Guided by the inspection data and service history, DPW-PBO replaced air handler unit 1 (AHU 1) at the Police Department. Per the above-mentioned plan, air handler unit 3 (AHU 3) is the next in line for replacement. If not replaced, the deterioration of the condensation pan and insulation may negatively impact the indoor air quality.
This project will include the disconnection and removal of the existing supply fan. A new Mainstream Fan wall system, including eight stacked fans and a wall controller, will take its place. Next, a standing seam plenum box with a hinged access man door will be installed. Lastly, the condensate drain pan will be replaced. All transition fittings and supply and return connecti...
Click here for full text